Bio
Experience
-
-
France
-
Construction
-
300 - 400 Employee
-
CONSTRUCTION AND TUNNEL SURVEYOR
-
Jan 2017 - Present
PROJECT: KURA WEST RIVER CROSSING, AZERBAIJAN (SOUTH CAUCASUS PIPELINE EXPANSION PROJECT)POSITION: SURVEYING AND GUIDED CHIEF KEY ACHIEVEMENTS: • Construction of tunnel by Pipe Jacking System D= 1.80m length 1010m, guided by UNS Universal Navigation System GNS (Herrenknetch).• Installation of a 48” OD pipeline into the micro tunnel and set up of the shaft riser• Grouting of the annular void between tunnel lining and pipeline with cementitious grout.
-
-
CONSTRUCTION AND TUNNEL SURVEYOR
-
Mar 2016 - Jan 2017
PROJECT: KURA EAST RIVER CROSSING, GEORGIA (SOUTH CAUCASUS PIPELINE EXPANSION PROJECT)POSITION: SURVEYING AND GUIDED CHIEF KEY ACHIEVEMENTS: • Structural monitoring shaft and Instrumentation-monitoring Railway (Train Georgia- Azerbaijan)• Construction of tunnel by Pipe Jacking System D= 1.80m length 605m, guided by UNS Universal Navigation System GNS (Herrenknetch).• Installation of a 48” OD pipeline into the micro tunnel and set up of the shaft riser• Grouting of the annular void between tunnel lining and pipeline with cementitious grout.
-
-
CONSTRUCTION AND TUNNEL SURVEYOR
-
Dec 2014 - Mar 2016
• Construction of tunnel by Segments System D= 2.5m length 1750m, guided by UNS Universal Navigation System GNS (Herrenknetch).• Construction of inlet and outlet chambers • Construction of bridges over the river Torres and the river Maria Aguilar• Urban works monitoring, Structural monitoring and tunnel convergence monitoring (charge of the work under the supervision of SolData Iberia).•
-
-
CONSTRUCTION AND TUNNEL SURVEYOR
-
Jun 2013 - Nov 2014
• Construction of tunnel by Pipe Jacking System D= 1.50m length 5500m, guided by UNS Universal Navigation System GNS-ELS-HWL (Herrenknetch).
-
CONSORCIO CICE-ICA-STYMA
-
Medellin, Colombia (South America)
-
CHIEF SURVEYOR
-
Sep 2012 - May 2013
-
Medellin, Colombia (South America)
PROJECT: TUNEL INTERCEPTOR NORTE DEL RIO MEDELLIN (EPM)POSITION: SURVEYING AND GUIDED CHIEF KEY ACHIEVEMENTS:• Construction of tunnel by Pipe Jacking System D= 2.20m length 4670m, guided by SLS- Microtunelling LT (VMT). • Construction of tunnel by Pipe Jacking System D= 2.40m length 3160m, guided by SLS- Microtunelling LT (VMT). • Construction of tunnel by Pipe Jacking System D= 1.20m length 500m, guided by SLS- Microtunelling LT (VMT).
-
CONSORCIO CANOAS
-
Bogota, Colombia (South America)
-
CHIEF SURVEYOR AND TUNNEL SURVEYOR
-
Nov 2010 - Sep 2012
-
Bogota, Colombia (South America)
PROJECT: CONSTRUCCIÓN INTERCEPTOR TUNJUELO CANOAS EN TÚNEL (EAAB). CONSTRUCCIÓN TÚNEL DE EMERGENCIA (EAAB). BOGOTA, COLOMBIA.POSITION: SURVEYING AND GUIDED CHIEF KEY ACHIEVEMENTS:• Construction of tunnel by Segments System D= 3.20m length 2500m, guided by TUNIS Navigation TBM (VMT).• Construction of tunnel by Segments System D= 4.20m length 8200m, , guided by TUNIS Navigation TBM (VMT).
-
BESSAC ANDINA S.A.
-
Bogota, Colombia (South America).
-
CONSTRUCTION AND TUNNEL SURVEYOR
-
Oct 2010 - Nov 2010
-
Bogota, Colombia (South America).
PROJECT: AUTOPISTA NORTE TRAMO II (AVN 1200) BOGOTA, COLOMBIA. POSITION: SURVEYING AND GUIDED CHIEF KEY ACHIEVEMENTS: • Construction of tunnel by Pipe Jacking System D= 1.20m length 820m, guided by UNS Universal Navigation System GNS-ELS-HWL (Herrenknetch).• Construction of wells intercept access by Caisson System
-
BESSAC ANDINA
-
Bogota, Colombia (South America)
-
CONSTRUCTION AND TUNNEL SURVEYOR
-
Aug 2010 - Oct 2010
-
Bogota, Colombia (South America)
PROJECT: CONSEJO CALLE 26 (AVN 1600) BOGOTA, COLOMBIA POSITION: SURVEYING AND GUIDED CHIEF KEY ACHIEVEMENTS: • Construction of tunnel by Pipe Jacking D= 1.60m length 840m, guided by UNS Universal Navigation System GNS-ELS-HWL (Herrenknetch). • Construction of wells intercept by Caisson System
-
CONSORCIO ITB - CSM BESSAC - CONCONCRETO
-
Bogota, Colombia (South America)
-
CONSTRUCTION AND TUNNEL SURVEYOR
-
Oct 2008 - May 2010
-
Bogota, Colombia (South America)
PROJECT: CONSTRUCCION TUNJUELO BAJO EN TUNEL (EAAB)POSITION: TUNNEL SURVEYORKEY ACHIEVEMENTS:• Construction of tunnel by Pipe Jacking System D= 2.45m, length 4800m, guided by UNS Universal Navigation System GNS (Herrenknetch).• Construction of tunnel by Pipe Jacking System D= 2.75m, length 3650m, guided by UNS Universal Navigation System GNS-ELS-HWL (Herrenknetch).• Construction of tunnel by Pipe Jacking System D= 1.60m, length 1000m, guided by UNS Universal Navigation System GNS-ELS-HWL (Herrenknetch).• Construction of tunnel by Pipe Jacking System D= 600mm, length 1000m, guided by UNS Universal Navigation System ELS (Herrenknetch).• Construction of handles residual sewage since 500mm to 1.20m• Construction of wells intercept access by the system display pre- excavated
-
BESSAC ANDINA
-
Bogota, Colombia (South America)
-
CONSTRUCTION AND TUNNEL SURVEYOR
-
Sep 2009 - Jan 2010
-
Bogota, Colombia (South America)
PROJECT: AUTOPISTA NORTE TRAMO I (AVN 1600)POSITION: SURVEYOR KEY ACHIEVEMENTS:• Construction of tunnel by Pipe Jacking System D= 1.60m length 620m, , guided by UNS Universal Navigation System GNS-ELS-HWL (Herrenknetch).• Construction of wells intercept access by Caisson System
-
CONSORCIO CANNAN LTDA/LARS LTDA
-
Bogota, Colombia (South America)
-
SURVEYOR
-
Jan 2009 - Dec 2009
-
Bogota, Colombia (South America)
PROJECT: CONSTRUCCION COLEGIO SAN JOSE MONTEBLANCO. BOGOTA, COLOMBIA POSITION: SUERVEYORKEY ACHIEVEMENTS:• Location, layout, town planning, roads and landscaping
-
Consorcio Las Granjas - DJG
-
Bogota, Colombia (South America)
-
SURVEYOR
-
Feb 2007 - Oct 2008
-
Bogota, Colombia (South America)
PROJECT: CONSTRUCCIÓN ALCANTARILLADO SANITARIO Y PLUVIAL DEL SECTOR INDUSTRIAL LAS GRANJAS (EAAB). POSITION: SURVEYOR KEY ACHIEVEMENTS: • Construction of box culvert in reinforced concrete, length 1500m• Construction of waste and sewage combined, length 1500m (GRP pipeline diameter 1.70 and 1.50. Novaloc diameter 900 – 600mm)• Design and construction of roads affected in rigid pavement MR-45 (approximately length 850m and flexible pavement 100m)
-
WESTERN ATLAS INTERNATIONAL, INC
-
Monte Agudo, Bolivia (South America)
-
SURVEYOR
-
Apr 2008 - Sep 2008
-
Monte Agudo, Bolivia (South America)
PROJECT: 3-D MONTE AGUDO. SANTA CRUZ DE LA SIERRA, BOLIVIA. (SOUTH AMERICA)POSITION: SURVEYOR KEY ACHIEVEMENTS: • Seismic and oil exploration
-
CONSORCIO PROYECTAR
-
Boyaca-Santander, Colombia (Suramerica)
-
TOPOGRAPHER CONTRACTOR
-
Mar 2006 - Jul 2007
-
Boyaca-Santander, Colombia (Suramerica)
PROJECT: PLAN 2500 INVIAS G-78 Y G-22, BOYACA Y SANTANDER, COLOMBIAPOSITION: TOPOGRAPHER CONTRACTORKEY ACHIEVEMENTS:• Design, reconstruction, paving and repaving roads G-78 Santander (Charala 7.8Km, Cantera-Encino 5.0km, Oiba-Guadlupe 15.0km and Suaita-Vado Real 4.0km) and G-22 Boyacá (Santa Maria- San Luis de Gaceno 22km)
-
CONSORCIO TUNEL 2006 - DJG
-
Bogota, Colombia (South America)
-
SURVEYOR
-
Oct 2006 - Jan 2007
-
Bogota, Colombia (South America)
PROJECT: ESTUDIOS, DISEÑOS Y CONSTRUCCIÓN DEL TÚNEL O PASO PEATONAL SUBTERRÁNEO ENTRE EL EDIFICIO NUEVO DEL CONGRESO Y EL CAPITOLIO NACIONAL, SUSCRITO CON EL SENADO DE LA REPUBLICA.POSITION: SURVEYOR KEY ACHIEVEMENTS:• Construction of tunnel-box in reinforced concrete 14.80m2, length 130m
-
CONSORCIO CANAL TIBANICA
-
Bogota, Colombia (South America)
-
SURVEYOR
-
Feb 2005 - Sep 2006
-
Bogota, Colombia (South America)
PROJECT: ELABORACIÓN DE LOS DISEÑOS DETALLADOS Y CONSTRUCCIÓN DEL CANAL TIBANICA BOMBEO Y EL INTERCEPTOR TERREROS ETAPA I (EAAB). POSITION: SURVEYOR KEY ACHIEVEMENTS:• Construction of canal Tibanica Bombeo (1200m) and construction box culvert (4.00 x 2.50 – length 1200m)• Construction intercept Terreros I ( D=1.30m length 3600m)• Construction maintenance channel via (length 1500m)• Construction of tunnel highway south (length 100m)
-
CONSORCIO CICON - KMA
-
Bogota, Colombia (South America)
-
TOPOGRAPHER CONTRACTOR
-
Nov 2004 - Jan 2005
-
Bogota, Colombia (South America)
PROJECT: REDES LOCALES DE ALCANTARILLADO EN LA LOCALIDAD DE SUBA (EAAB). POSITION: TOPOGRAPHER CONTRACTOR KEY ACHIEVEMENTS:• Location, layout and construction of sanitary and storm sewer local networks, road suitability of neighborhoods: San Pedro, Santa Cecilia I and II, Santa Rita, Villa Cindy, Verona e Isabella and Lisboa• Repair of water supply networks affected
-
UNION HIMEXA DIEGO-JARAMILLO
-
Bogota, Colombia (South America)
-
TOPOGRAPHER CONTRACTOR
-
Jan 2004 - Nov 2004
-
Bogota, Colombia (South America)
PROJECT: CONSTRUCCIÓN ESTACIÓN DE BOMBEO CAFAM – PONDAJE CAFAM – DISEÑO Y CONSTRUCCIÓN ESTACIÓN PROVISIONAL DE BOMBEO LISBOA – REALCE JARILLÓN COSTADO ORIENTAL RÍO BOGOTÁ – SECTOR GAVILANES (EAAB). BIAPOSITION: TOPOGRAPHER CONTRACTOR KEY ACHIEVEMENTS:• PUMPING STATION LISBOA: Location and cast piles pre- excavated, construction of reinforced screens depth 15m, steel pipe fitting, CCP, GRP and concrete, mechanical electronic assemblies, town planning in roads, sidewalks, aqueducts and etc.… • ENHANCEMENT DYKE LISBOA RIVER: dyke location and batter line location approximately 6km from dyke, earthworks - excavation approximately 80.000m3 clay and subbase 25.000m3
-
MARIO GERMAN GARCIA G.- GARPER
-
Bogota, Colombia (South America)
-
TOPOGRAPHER CONTRACTOR
-
Dec 2002 - Dec 2003
-
Bogota, Colombia (South America)
PROJECT: CANAL CUNDINAMARCA TRAMO III (AV. PRIMERO DE MAYO-CANAL TINTAL) (EAAB)POSITION: TOPOGRAPHER CONTRACTOR KEY ACHIEVEMENTS: • Earthworks – excavation approximately 170.000m3, The Corso.• Concrete costing – length 975m• Stakeout road maintenance and construction – approximate length 1km• Sewer pipe installation and aqueduct
-
INA BROMCO CIA LTDA
-
Bogota, Colombia (South America)
-
TOPOGRAPHER CONTRACTOR
-
Dec 2000 - Apr 2003
-
Bogota, Colombia (South America)
PROJECT: BOX – COULVERT SALITRE Y OBRAS COMPLEMENTARIAS (EAAB)POSITION: TOPOGRAPHER CONTRACTOR KEY ACHIEVEMENTS: • Earth movements in the lagoon N.1- excavation approximately 630.000m3 – embankments approximately 400.000m3 • Installation of piping manifolds Juan Amarillo 1-2 and manifold Tibabuyes – length 1500m, diameters 2.3m, 2.00m, 1.7m, 1.6m and 1.5m • Pipe installation HF Aqueduct from de tank Suba to Lagoon N.1- Length 2500m• 1967m construction opencast channel, Box – Culvert length 4.5km• Northwest dyke construction – Embankment approximately 45.000m3 • Landscaping, road and cycling trail 1.5km
-
UNION TEMPORAL TIMIZA LTDA
-
Bogota, Colombia (South America)
-
TOPOGRAPHER CONTRACTOR
-
Oct 2000 - Dec 2000
-
Bogota, Colombia (South America)
PROJECT: CONSTRUCCION PARQUE TIMIZA – VILLA DEL RIO. BOGOTA, COLOMBIA POSITION: TOPOGRAPHER CONTRACTOR KEY ACHIEVEMENTS:• Location, layout, town planning, roads and landscaping
-
CONSORCIO ECOPARQUES LTDA
-
Bogota, Colombia (South America)
-
SURVEYOR
-
Jan 2000 - Oct 2000
-
Bogota, Colombia (South America)
PROJECT: CONSTRUCTION PARQUE ALCAZARES, NICOLAS DE FEDERMAN, CARMEN DE LA LAGUNA Y AUTOPISTA NORTE. BOGOTA, COLOMBIA POSITION: SURVEYORKEY ACHIEVEMENTS:• Location, layout, town planning, roads and landscaping
-
CONSORCIO CANNAN LTDA/LARS LTDA
-
Bogota, Colombia (South America)
-
SURVEYOR
-
Jan 1999 - Dec 1999
-
Bogota, Colombia (South America)
PROJECT: CONSTRUCCION COLEGIO SAN JOSE MONTEBLANCO. POSITION: SURVEYORKEY ACHIEVEMENTS:• Location, layout, town planning, roads and landscaping
-
WESTERN ATLAS INTERNATIONAL INCORPORATED
-
Monte Agudo, Bolivia (South America)
-
SURVEYOR
-
Apr 1998 - Sep 1998
-
Monte Agudo, Bolivia (South America)
PROJECT: 3-D MONTE AGUDO. SANTA CRUZ DE LA SIERRAPOSITION: SURVEYOR KEY ACHIEVEMENTS: • Seismic and oil exploration
-
3-D GEOPHYSICAL INC
-
Monte Agudo, Bolivia (South America)
-
SURVEYOR
-
Mar 1998 - Apr 1998
-
Monte Agudo, Bolivia (South America)
PROJECT: 3-D MONTE AGUDO. SANTA CRUZ DE LA SIERRA, BOLIVIA. (SOUTH AMERICA)POSITION: SURVEYOR KEY ACHIEVEMENTS: • Seismic and oil exploration
-
SOLID STATE INTERNATIONAL INC. C.A
-
Aguarague, Bolivia (South America)
-
SURVEYOR
-
Sep 1997 - Apr 1998
-
Aguarague, Bolivia (South America)
PROJECT: 2-D JUAN LATINO AND 2-D AGUARAGUE. SANTA CRUZ DE LA SIERRAPOSITION: SURVEYOR KEY ACHIEVEMENTS: • Seismic and oil exploration
-
A.V. INGENIEROS LTDA
-
Bogota, Colombia (South America)
-
TOPOGRAPHER CONTRACTOR
-
Dec 1996 - Aug 1997
-
Bogota, Colombia (South America)
PROJECT: URBANIZATION AV. EL MIRADOR ENGATIVA.POSITION: TOPOGRAPHER CONTRACTOR KEY ACHIEVEMENTS: • Location, layout, town planning, riding routs and landscaping
-
LOBO-GUERRERO CONSTRUCTORES LTDA
-
Villeta-Barbosa, Colombia (South America)
-
SURVEYOR
-
Apr 1996 - Oct 1996
-
Villeta-Barbosa, Colombia (South America)
PROJECT: MANIZALES – VILLETA COL. – MIRAVALLES RIVER, MONIQUIRA-BARBOSA, COLOMBIA. POSITION: SURVEYOR KEY ACHIEVEMENTS:• Location, layout and construction of highways and roads
-
WESTERN ATLAS INTERNATIONAL INCORPORATED
-
Casanare, Colombia (South America)
-
SURVEYOR
-
Dec 1995 - Mar 1996
-
Casanare, Colombia (South America)
PROJECT: 3-D UNETE NORTH AND 2-D VOLCANERAS.POSITION: SURVEYORKEY ACHIEVEMENTS:• Seismic and oil exploration
-
CONSTRUCTORA HORA Y CF
-
Bogota, Colombia (South America)
-
TOPOGRAPHER CONTRACTOR
-
Feb 1995 - Nov 1995
-
Bogota, Colombia (South America)
PROJECT: URBANIZATION PUERTO SOL CAFAM, ETAPA V. POSITION TOPOGRAPHER CONTRACTOR KEY ACHIEVEMENTS: • Location, layout, town planning, routs and landscaping
-
LIBARDO RUBIANO - LARS LTDA
-
Bogota, Colombia (South America)
-
SURVEYOR
-
Nov 1994 - Jan 1995
-
Bogota, Colombia (South America)
PROJECT: PLANIMETRIC AND ALTIMETRIC SURVEY OF 60 ROUTS. (BOLIVAR CITY). POSITION: TOPOGRAPHER CONTRACTORKEY ACHIEVEMENTS:• Design and location of routs
-
ORGANIZACION LUIS CARLOS SARMIENTO LTDA.
-
Bogota, Colombia (South America)
-
ASSISTANT SURVEYING
-
Apr 1990 - Jan 1995
-
Bogota, Colombia (South America)
PROJECT: URBANIZATIONS: VILLA ALSACIA, VILLA DE LOS ALPES, VILLA MAYOR, VILLA DEL PINAR AND VILLAS DE ARANJUEZ. BOGOTA, COLOMBIA POSITION: ASSISTANT SURVEYING KEY ACHIEMENTS: • Location, layout, town planning and routs
-
-
Education
-
2006 - 2013District University Francisco Jose de Caldas
CIVIL ENGINEER, Ninth semester, CONSTRUC -
1992 - 1995District University Francisco Jose de Caldas
SURVEYING TECHNOLOGY, Surveying Technology/Surveying
Suggested Services
This profile is unclaimed. These are suggested service rates with 0% commision upon successful connection
Industry Focus. “Construction”
Need a custom project? We'll create a solution designed specifically for your project.
References
Social Profiles
Community