Tyler Bassinger, P.E.

Project Manager at Toebe Construction LLC
  • Claim this Profile
Contact Information
us****@****om
(386) 825-5501
Location
Detroit Metropolitan Area

Topline Score

Topline score feature will be out soon.

Bio

Generated by
Topline AI

You need to have a working account to view this content.
You need to have a working account to view this content.

Credentials

  • P.E.
    Nevada State Board of Professional Engineers and Land Surveyors
    Jan, 2012
    - Nov, 2024
  • EIT
    NCEES
    Nov, 2007
    - Nov, 2024

Experience

    • United States
    • Construction
    • 1 - 100 Employee
    • Project Manager
      • Oct 2023 - Present

    • United States
    • Construction
    • 300 - 400 Employee
    • Project Manager
      • Jan 2022 - Oct 2023

    • United States
    • Construction
    • 1 - 100 Employee
    • Underground Operations Manager
      • Jan 2021 - Dec 2021

    • Project Manager
      • Apr 2019 - Dec 2020

    • United States
    • Construction
    • 500 - 600 Employee
    • Project Manager
      • May 2017 - Nov 2018

      TxDOT – 0543-02-055 – FM 359 Richmond - $27,124,548 Elevated T bridge at intersection of FM 359 and US 90A. Including 4 MSE walls, 20,000 LF of RCP and RCB, and 64,800 SY of CRCP. Completed project buyout, setup budget, created P6 schedule, project execution and resource allocation, coordination with owner and subcontractors, provide training and mentoring to new field engineers. First job to be successfully integrated into new SAP cost/quantity tracking system.

    • Superintendent
      • Apr 2015 - May 2017

      TxDOT – SH 99 Grand Parkway – Segment F1, F2, G - $1,100,000,000 Large scale design/build project to construct new toll loop around the city of Houston. Successfully assisted with bidding process, completed design feasibility studies during design phase, built and maintained resource loaded P6 schedule, coordinated with landowners during ROW acquisitions and utility relocations, supervised on site field work in superintendent capacity for mass haul embankment of over 2.5 million… Show more TxDOT – SH 99 Grand Parkway – Segment F1, F2, G - $1,100,000,000 Large scale design/build project to construct new toll loop around the city of Houston. Successfully assisted with bidding process, completed design feasibility studies during design phase, built and maintained resource loaded P6 schedule, coordinated with landowners during ROW acquisitions and utility relocations, supervised on site field work in superintendent capacity for mass haul embankment of over 2.5 million CY, subgrade stabilization, underground storm sewer, MSE walls, and soil nail walls. Successfully managed critical path construction of an underpass near Hooks Airport. Coordinated all crane work with the FAA. Managed and assisted with design of traffic control plans to maintain traffic throughout construction. Developed dewatering system for underpass area during soil nail wall excavation to limit delays caused by excessive rain.

    • Project Engineer
      • Jul 2012 - Apr 2015

      TxDOT – SH 99 Grand Parkway – Segment F1, F2, G - $1,100,000,000 Large scale design/build project to construct new toll loop around the city of Houston. Successfully assisted with bidding process, completed design feasibility studies during design phase, built and maintained resource loaded P6 schedule, coordinated with landowners during ROW acquisitions and utility relocations, supervised on site field work in superintendent capacity for mass haul embankment of over 2.5 million… Show more TxDOT – SH 99 Grand Parkway – Segment F1, F2, G - $1,100,000,000 Large scale design/build project to construct new toll loop around the city of Houston. Successfully assisted with bidding process, completed design feasibility studies during design phase, built and maintained resource loaded P6 schedule, coordinated with landowners during ROW acquisitions and utility relocations, supervised on site field work in superintendent capacity for mass haul embankment of over 2.5 million CY, subgrade stabilization, underground storm sewer, MSE walls, and soil nail walls.

    • United States
    • Construction
    • 100 - 200 Employee
    • Project Manager
      • Apr 2012 - Jul 2012

      Responsible for meeting with clients and preparing geotechnical engineering solutions including jet grouting, helical piles, and soil nail walls in order to meet specific needs. Prepared quotes and contracts, procured materials, scheduled work and maintained onsite supervision through completion. Responsible for meeting with clients and preparing geotechnical engineering solutions including jet grouting, helical piles, and soil nail walls in order to meet specific needs. Prepared quotes and contracts, procured materials, scheduled work and maintained onsite supervision through completion.

    • United States
    • Wholesale Building Materials
    • 700 & Above Employee
    • Project Engineer
      • Jan 2008 - Apr 2012

      Responsible for tracking daily quantities and costs, Handling project submittals, RFI’s and CCA’s, Maintaining a good relationship with the owner, Performing monthly cost projections, Coordinating subcontractors to perform work, Maintaining and updating the project schedule Responsible for tracking daily quantities and costs, Handling project submittals, RFI’s and CCA’s, Maintaining a good relationship with the owner, Performing monthly cost projections, Coordinating subcontractors to perform work, Maintaining and updating the project schedule