Engineering Professional G+12
Dubai MunicipalityFeb, 2019- Nov, 2024 -
Project Management Professional (PMP)
Project Management InstituteMar, 2023- Nov, 2024 -
Practicing Engineer
Abu Dhabi City MunicipalityApr, 2023- Nov, 2024 -
Equivalency Certificate in Civil Engineering
Ministry of Education – UAE -
Member of the Society of Engineers UAE
Society of Engineers-UAE
Experience
-
SECURE ENGINEERING LLC
-
United Arab Emirates
-
Civil Engineering
-
100 - 200 Employee
-
Resident Engineer
-
May 2021 - Present
Project: Modification & construction of the main gate for GHQ Abu Dhabi Police (ongoing)Project Description: Visitors Building + Guard Building + Main Gate + Soft and Hard Landscape Client: Abu Dhabi PoliceContractor: Force 10 UAE Duration: 12 Months Project coast: 50 Million AEDProject: AL Bateen VIP Majles 1265 m2 (completed)Project Description: G+1+ Soft and Hard Landscape Client: Ministry of Residential affairsContractor: A&M international general contracting Duration: 10 Months Project coast: 45 Million AEDProject: Construction of boundary wall and gates for heavy vehicles parking 2174 LMClient: ITC (Integrated Transport Center) Contractor: Express facilities management LLCDuration: 8 Months Project coast: 15 Million AED Show less
-
-
Construction Manager
-
Sep 2018 - Apr 2021
Project: Al Marfa Police Station Project Description: B.F+G.F+F.L+S.F+3rd.F+Roof + Services Block (G+1) + Substation + Security rooms 2 no’s+ Soft and Hard Landscape Client: Ministry of Interior Abu Dhabi PoliceEmployer: Musanada Consultant: AL Torath InternationalDuration: 12 MonthsProject coast: 90 Million AEDProject: Design & construction of Pre Fab OfficesProject Description: Main Building (G+2), GYM building, Reception Building, Theater, Substation Building, Security room Building 2 no’s, Soft and Hard Landscape Client: Ministry of Presidential Affairs Duration: 12 Months Project coast: 60 Million AEDProject: Design and Construction of Private Villa Project Description: B+G.f+F.F+ 2nd.F+Roof + Swimming Pool + Interior Design + Soft and Hard Landscape Consultant: Dar EL Emara Duration: 12 Months Project coast: 50 Million AEDProject: Demolition and Reconstruction of Boundary walls and Gates of Umm Al Nar Cemetery, Al Bateen Cemetery and Mahawi Cemetery with Surveillance Cameras+Landscape Client: Abu Dhabi Municipality Consultant: Parsons InternationalDuration: 9 Months Project coast: 30 Million AED Show less
-
-
-
Seidco General Contracting Company
-
United Arab Emirates
-
Construction
-
100 - 200 Employee
-
Civil Project Engineer
-
Feb 2017 - Sep 2018
Position: Project Engineer Project: Dubai Hills Estate-P5AB Park Point (4 RESIDENTIAL BUILDINGS G+2P+12F+Roof) Client: EMAAR PROPERTIES and MEERAS Employer: Ellisdon Corporation Consultant: National Engineering Bureau (NEB) Duration: 2 years Project coast: 232 Million AED Position: Project Engineer Project: Dubai Hills Estate-P5AB Park Point (4 RESIDENTIAL BUILDINGS G+2P+12F+Roof) Client: EMAAR PROPERTIES and MEERAS Employer: Ellisdon Corporation Consultant: National Engineering Bureau (NEB) Duration: 2 years Project coast: 232 Million AED
-
-
-
Al BURJ Engineering consultants
-
United Arab Emirates_Dubai
-
Site Civil Engineer
-
Nov 2014 - Jan 2017
Position: Civil Engineer Project: THE LIVING LEGENDS PROJECT (500 VILLAS AND 12 RESIDENTIAL BUILDINGS) Client: Tanmiyat Global Real Estate Contractor: Delta Emirates Contracting LLC Project coast = 2 Billion AED Position: Civil Engineer Project: THE LIVING LEGENDS PROJECT (500 VILLAS AND 12 RESIDENTIAL BUILDINGS) Client: Tanmiyat Global Real Estate Contractor: Delta Emirates Contracting LLC Project coast = 2 Billion AED
-
-
-
SYSTRA USA
-
United States
-
Rail Transportation
-
100 - 200 Employee
-
civil inspector
-
Nov 2012 - Nov 2014
Dubai Tram Project. • Working as a Site Civil Engineer in Dubai Tram Depot : purpose of Execute (Operation & Administration building-Washing machine building –(Main entrance, TPS, Generator, chiller, pumps) building- Drivers building) Supervise Various Activites as below:- • Steel Structure (Erection–Painting-Roof Cladding–Wall Cladding-Composite Steel Floor Decking • Buildings (Formwork, Reinforcement and Casting for Various Concrete elements, Footing – Core walls – Ground Beam – Columns- Beams – Slabs). • Finishing works (block works_ plaster_ painting_ raised floor_ tiles_ wall cladding (GRC cladding)_partition walls_ false ceiling). • Foundation track slabs. • Piles works ( Excavation- Reinforcement Cage-Casting and Testing) • Field inspection and supervision to ensure compliance with approved procedures, drawing and project specifications. • Performed regular surveys to ensure that the work is progressing according to the plan. • Coordinated with the contractor to resolve any problems. • Inspected the construction site on a daily basis to ensure that all safety and quality procedures are adhered to. • Prepared reports for the submission work carried as per the construction plans and drawings. • Prepared daily and weekly reports of the construction process and made any changes to the plan if necessary. • Precast yard (Manholes – Pulling Chambers – Gullys – Light Pole) • Observe site safety procedures. • Supervision and Inspection of all construction activities carried out by contractor on site. • Study and understand project scope and specifications as well as ITPs (Inspection Test Plans) and method statements. • Receive RFI and carry out inspection of Equipment /Construction as per the ITP, identify any discrepancies and generate Non Conformance report. Ensure corrective action on the above thereby ensuring the closure of the NCR raised. • Ensuring all materials delivered to site are inspected and confirm to specified requirements. Show less
-
-
-
-
Site Civil Engineer
-
Oct 2011 - Oct 2012
• Buildings (Formwork, Reinforcement and Casting for Various Concrete elements, Footing – Core walls – Ground Beam – Columns- Beams – Slabs). • Finishing works (block works_ plaster_ painting_ tiles) • Prepared daily and weekly reports of the construction process and made any changes to the plan if necessary. • Prepared reports for the submission work carried as per the Construction plans and drawings. • Buildings (Formwork, Reinforcement and Casting for Various Concrete elements, Footing – Core walls – Ground Beam – Columns- Beams – Slabs). • Finishing works (block works_ plaster_ painting_ tiles) • Prepared daily and weekly reports of the construction process and made any changes to the plan if necessary. • Prepared reports for the submission work carried as per the Construction plans and drawings.
-
-