Nawah Energy Company
-
United Arab Emirates
-
Oil and Gas
-
700 & Above Employee
-
Scheduling Specialist
-
juil. 2019 - - aujourd’hui
I have been working with the initial start-up teams focusing on reactor fueling and power ascension testing (PAT) since 2019. My role is to build and maintain level 4 schedules with input from the operation and maintenance teams incorporating all test procedures and surveillances to enable us to reach mode 6 and commence fuel load. Following this working with the PAT teams which focused on reactor assembly, test plateaus, initial criticality and then raising the reactor power through stages to 100% before becoming operational. My main role is to establish and maintain critical and sub-critical paths which can be monitored and reported to managers and major stakeholders. Other elements of my role are adding emergent and repair work to the schedule that may emerge from discovery as the teams perform surveillance and performance testing. This is then linked into the critical path looking for potential pushes. I am currently working on unit 3 after successfully working on units 1&2 which are now operational.Working in the Fuel Load and PAT Control Centre is essentially like working in an outage environment. Dealing with emergent work and daily scope changes, which involves many scheduling changes and subsequent reviews. Having to work in the live schedule requires the scheduler to have a good understanding of processes and procedures while working under pressure in a very dynamic environment. The position requires good plant and nuclear knowledge to work directly with all the disciplines to ensure that all scope is correctly scheduled and in-line with recourse and plant availability.Current role includes:• Managing critical path movement, reporting to major stakeholders and focus teams.• Advising the FL & PAT leads on critical & sub-critical activities with possible interventions.• Working with the operations teams to ensure all system line-up, ST, PT are scheduled in a timely manner to support Mode changes with support from I&C and Electrical teams.
-
-
-
Costain Group PLC
-
United Kingdom
-
Civil Engineering
-
700 & Above Employee
-
Senior Project Control Engineer
-
sept. 2018 - juil. 2019
Dry Fuel Store Project. The principal objective of the project was to successfully transfer and load Seven HI-STORM cask with spent fuel assemblies into the DFS Facility at SZB. The benefit of this project is to facilitate the release of further storage capacity in the reactor fuel building ponds to enable continued generation of the station. This then allowed continued operation until 2035. My role was to build level 3 cost loaded programs using Primavera P6 to facilitate the loading ensuring that all the correct processes and procedures had been captured in the programs.
-
-
-
-
Senior Scheduler
-
août 2017 - sept. 2018
Contracted by Turner & Townsend to EDF as a Senior Scheduler also the Lead Scheduler for the Conventional Island Program team on the HPC Nuclear New Build Project. As part of the Turbine Group, my scope of work covered the engineering studies, design, procurement, manufacture, transport and erection on site of the two 750mw turbines and associated plant and equipment for the new EPR, which is under construction on the west coast at Hinkley Point. The budget for this Turnkey contract was 1.8 billion and due to complete in 2026. As part of the CI team, my main role was to work collaboratively with the contractors to ensure that their submitted schedule were maintained to a high standard and adhering to the works information supplied to them by NNB. I worked closely with the Project Manager, Commercial team, Design Engineers, Risk Managers, Document Controllers and Cost Engineers to maintain the schedules to a high level.My responsibility included:• Overseeing junior schedulers within the Conventional Island team to ensuring that all process and procedures were followed correctly. Updating the team with information from the Lead team meetings.• Working closely with contractors and site schedulers to validate their programme information. • Responsible for the Analysis, Review and Assurance of supplier level three programmes and associated data using proscribed processes and tools.• Review submitted schedules via CEMAR with a view of accepting or rejection the schedule using NEC principles.• Updating the main overarching programme. The IWS (Integrated Work Schedule).• Provide performance reporting, analysis support and recommendations to the Project Manager.• Attend workshops and meetings with other project planners to manage and facilitate interfaces and interdependencies.• Travelling to France to liaise with the design teams and attending conventional Island program progress reviews.
-
-
-
Rullion
-
United Kingdom
-
Staffing and Recruiting
-
200 - 300 Employee
-
Project Control Engineer
-
oct. 2012 - août 2017
Contracted by Rullion to EDF as the Investment Delivery Project Control Engineer (PCE) for outage related projects. My role involved working on one of the outage critical projects the 10 yearly inspections of the reactor vessel which includes the building of a full-scale mock-up for training, equipment testing and installation of core barrel samples. I was also PCE for the stations Japanese Earthquake Response Program. The JER Projects had been implemented on all EDF Power Stations as a direct response to the Fukushima power plant disaster. The projects covered five major modifications to existing systems in the event of a ‘Beyond Basis Design’ occurrence. All modifications were underpinned by 16 cost-loaded schedules, which had a combined budget of £30 million.
-
-
-
Scantec Recruitment
-
United Kingdom
-
Staffing and Recruiting
-
1 - 100 Employee
-
Lead Scheduler
-
juin 2011 - oct. 2012
Contracted by Scantec to Magnox as a Lead Scheduler to Magnox Ltd as part of the accelerated decommissioning planning team. I was assigned as the project scheduler within the FED (Fuel Element Debris) Team. This was a £100 million project, which was designed to enable the retrieval, dissolution and abatement of legacy radioactive materials left over from the power production period of the station. The project was on the stations critical path and was essential to the early care and maintenance of Bradwell.
-
-
-
Rullion
-
United Kingdom
-
Staffing and Recruiting
-
200 - 300 Employee
-
Outage Project Scheduler
-
août 2008 - juin 2011
Contracted by Rullion to EDF as an Outage Project Scheduler. I held overall responsibility for the preparation of detailed level 4 plans for the Cooling Water and Steam & Feed Systems. Contracted by Rullion to EDF as an Outage Project Scheduler. I held overall responsibility for the preparation of detailed level 4 plans for the Cooling Water and Steam & Feed Systems.
-
-
-
Interserve
-
United Kingdom
-
Construction
-
700 & Above Employee
-
Resource Scheduler
-
janv. 2007 - août 2008
Resource Planner, Sizewell B PowerStation. Responsibilities included: Resource scheduling over 2000 Scaffold & Insulation activities, reviewing logic, agreeing manning levels and developing histograms.
-
-
Maintenance Scheduler
-
sept. 2004 - août 2008
Maintenance scheduler/Senior Supervisor, Sizewell B PowerStation. Responsibilities included Reviewing planned work on a 13-week rolling program (AP928) and agreeing manning levels with the station cycle schedulers.
-
-