Experience

    • Indonesia
    • Construction
    • 1 - 100 Employee
    • Project Control Engineer
      • Mar 2022 - Present

    • Indonesia
    • Industrial Machinery Manufacturing
    • 100 - 200 Employee
    • Project Control Engineer
      • Mar 2021 - Feb 2022

  • PT. Bekasap Main Indonesia
    • Pekanbaru, Riau, Indonesia
    • Project Estimator
      • Feb 2020 - Mar 2021

  • PT. CTI
    • Kendari, Makassar, Semarang, Jakarta
    • Project Planner & Control
      • May 2016 - Feb 2020

      1. EPC Project DSSP Power - PLTU Kendari 3 PT. PLN.,Sulawesi Tenggara. Indonesia. 2. EPC Project Bosowa - PLTU Bosowa, Jeneponto, Sulawesi Selatan, Indonesia. 3. EPC Project - GITET 500 kV Batang Extention, GI 150 kV Batang New 1. EPC Project DSSP Power - PLTU Kendari 3 PT. PLN.,Sulawesi Tenggara. Indonesia. 2. EPC Project Bosowa - PLTU Bosowa, Jeneponto, Sulawesi Selatan, Indonesia. 3. EPC Project - GITET 500 kV Batang Extention, GI 150 kV Batang New

    • Site Manager
      • Dec 2015 - May 2016

      Perform a technical, organisational and supervisory role on construction projects, setting out and determining the location for above and underground infrastructural installations involved in construction operations. Responsibility for site security, health and safety and the organisation and supervision of material and human resources. Perform a technical, organisational and supervisory role on construction projects, setting out and determining the location for above and underground infrastructural installations involved in construction operations. Responsibility for site security, health and safety and the organisation and supervision of material and human resources.

  • PT. Nira Murni Konstruksi
    • Chevron, EPC Dumai, Balam GS Project.
    • Billing Engineer
      • Aug 2015 - Dec 2015

    • Construction
    • 700 & Above Employee
    • Project Planning & Control
      • Dec 2012 - Aug 2015

      To observe activities of contractor work party accordingly and carry out evaluation of work volume and cost price per unit. Re measurement of quantities like checking and verifying subcontractor's remeasurement submission. Monitor subcontractor complience with the contract and condition closely and alert management and site representative of corrective action to be taken to avert potensial claim situation. Regular site visit to verification of construction quantities have been installing. Show less

  • PT. Nira Murni Kontruksi
    • Chevron - Dumai , Balam GS, Duri Heavy Oil Operation Unit.
    • Lead Scheduler
      • Aug 2012 - Dec 2012

      Determining the critical path of the program based on schedule progress and established task dependencies. Perform schedule analysis in support of assigned programs and projects. Perform schedule variance analysis by comparing baseline to schedule. Ensure compliance with internal program procedures and project control system guidelines. Participate in scheduling status reviews. Manages project risks, issues, goals, and priorities. Prepares, implements, monitors, and updates the project plan. Show less

  • PT Multi Structure
    • Chevron - Duri Heavy Oil Operation Unit, Riau.
    • Project Control Engineer
      • Jun 2009 - Aug 2012

      Establishing work methods & work assignments require phase starts at the kick-off meeting,clarification of contract and / or letter of intent. Will involve developing in the actual physical progress measurement based on the percent complete of each activity and / or deliverable. Shall prepare and submit from commencement date, for approval a written procedure identifying the specific methods, form, techniques proposes to use in project control. Establishing work methods & work assignments require phase starts at the kick-off meeting,clarification of contract and / or letter of intent. Will involve developing in the actual physical progress measurement based on the percent complete of each activity and / or deliverable. Shall prepare and submit from commencement date, for approval a written procedure identifying the specific methods, form, techniques proposes to use in project control.

    • Indonesia
    • Construction
    • 1 - 100 Employee
    • Project Planning & Control
      • Feb 2009 - Jun 2009

  • Rifansi Daekyung Consortium
    • Chevron - Duri Heavy Oil Operation Unit.
    • Project Control
      • Feb 2007 - Aug 2007

      Infrastructure Maintenance at Heavy Oil Operation Unit in Duri Oil Field of PT. Chevron pacific Indonesia (CPI) Infrastructure Maintenance at Heavy Oil Operation Unit in Duri Oil Field of PT. Chevron pacific Indonesia (CPI)

  • PT. Smart Indonesia
    • Medan, Sumatera Utara.
    • Mechanical Engineer
      • Nov 2002 - Aug 2005

      To evaluate findings in inspection of broken productions equipment, machine and to find out how it happened and to give corrective and preventive action. Conduct all work in compliance with Quality, Health and Safety. To evaluate findings in inspection of broken productions equipment, machine and to find out how it happened and to give corrective and preventive action. Conduct all work in compliance with Quality, Health and Safety.