Nicolas DUMEZ
Responsable d'essai at Framatome- Claim this Profile
Click to upgrade to our gold package
for the full feature experience.
Topline Score
Bio
0
/5.0 / Based on 0 ratingsFilter reviews by:
Experience
-
Framatome
-
France
-
Nuclear Electric Power Generation
-
700 & Above Employee
-
Responsable d'essai
-
Oct 2019 - Present
France
-
-
nuclear power plant test engineer
-
Sep 2017 - Oct 2019
Chalon-sur-Saône, Bourgogne, France
-
-
Commissioning Engineer
-
Dec 2015 - Aug 2017
Olkiluoto Finlande Commissionning of essential service water system (sea water) - Execution of preliminaries test on the power plant functional systems - Control of the hardware functionality, low voltage distribution check, isolation control of auxiliary motors… - Identify and analyze technical issues and propose solutions to the engineering - Execution of the global testing process with the customer for the final acceptance
-
-
-
Fives
-
India
-
Information Technology and Services
-
1 - 100 Employee
-
Project Engineer
-
Jan 2015 - Dec 2015
Villeneuve d'ascq - Coordination of projects (technical part), most particularly for process and general installation. - Equipment technical manager - Customer interlocutor
-
-
-
Cryostar
-
France
-
Industrial Machinery Manufacturing
-
400 - 500 Employee
-
LNG process commissioning Engineer
-
Dec 2013 - Dec 2014
international - Commissioning and test during sea trial (offshore) of LNG process on super tankers (logics check of the control system, instrumentation tuning, resolution process issues, test of gas compressors and adjustment of surge protections, management of technicians teams)
-
-
-
GE Power & Water
-
Mexico
-
Electric Power Generation
-
400 - 500 Employee
-
Commissioning Engineer
-
Sep 2008 - Dec 2013
international - Power plant transfer supervision from erection to commissioning of the different systems and equipment of a twin gas turbines GE-209FB power plant. - Management and resolution of the erection and commissioning punchlist. - Shipping and transportation follow up for the whole plant equipments (valves, pumps, spare parts, tools…). - Steam turbine steam quality supervising in order to respect the equipment tolerance threshold - Execution of preliminaries test on the power… Show more - Power plant transfer supervision from erection to commissioning of the different systems and equipment of a twin gas turbines GE-209FB power plant. - Management and resolution of the erection and commissioning punchlist. - Shipping and transportation follow up for the whole plant equipments (valves, pumps, spare parts, tools…). - Steam turbine steam quality supervising in order to respect the equipment tolerance threshold - Execution of preliminaries test on the power plant functional systems (firefighting, lube oil, fuel gas, cooling water, gas turbine, steam turbine…) - Control of the hardware functionality, low voltage distribution check, isolation control of auxiliary motors… - Identify and analyze technical issues and propose solutions to the engineering - Execution of the global testing process with the customer for the final acceptance - Weekly report - Final inspection test in GE’s manufacturer’s factories (China, USA, Italy, Slovenia, and Poland) for gas turbine auxiliary skids before shipping and erection on field. - Factory test of gas turbines auxiliary skids (oil, fuel gas, atomizing air, water injection) - Check of the equipment conformity compared the different drawing (P&ID’s and electrical diagrams) - Performing of preliminaries test - Tuning of necessary devices before shipping (VPR, transmitters, switches…) - Functional test under pressure with different load rates - Ensure the results conformity compared to the specification - Reporting to the commissioning team and quality department of the issues Show less
-
-
Education
-
Université de Reims Champagne-Ardenne
Master mécanique et thermique, génie thermique et énergie -
Université du Littoral Côte d'Opale
DUT génie thermique et énergie