Quantity Surveyor (Construction of Kizad Head Quarters for Abu Dhabi Ports, Abu Dhabi) at Ali & Sons Contracting Company - Sole Proprietorship LLC- Claim this Profile
Click to upgrade to our gold package
for the full feature experience.
Topline Score
Bio
Experience
-
Ali & Sons Contracting Company - Sole Proprietorship LLC
-
United Arab Emirates
-
Construction
-
1 - 100 Employee
-
Quantity Surveyor (Construction of Kizad Head Quarters for Abu Dhabi Ports, Abu Dhabi)
-
Aug 2021 - Present
Abu Dhabi, United Arab Emirates A Monthly Payment Application (IPA). A.01 Work Progress Break down as per Original Contract. A.02 Work Progress Break down as per issued VO's. A.03 Work Progress Break down for Variation on Account (items under approval without VO from Engineer/Employer). A.04 Material On Site as per the Contract. A.05 Follow Up with Engineer till IPC is issued. B Variations. B.01 Submitting timely Notices as per Contract B.02 Submitting Particular details to the Engineer and further… Show more A Monthly Payment Application (IPA). A.01 Work Progress Break down as per Original Contract. A.02 Work Progress Break down as per issued VO's. A.03 Work Progress Break down for Variation on Account (items under approval without VO from Engineer/Employer). A.04 Material On Site as per the Contract. A.05 Follow Up with Engineer till IPC is issued. B Variations. B.01 Submitting timely Notices as per Contract B.02 Submitting Particular details to the Engineer and further follow-ups till VO is issued. B.03 Preparation of Potential Variation Schedule for Employer's information to know overall Expected final Contract Value. C Sub Contractor Payments. C.01 Certifying monthly payments to the Subcontractors as per Subcontract agreement. C.02 Tracking back charges to the subcontractors as per their scope of work and also from the construction team. C.03 Follow up with Advance Payment guarantee and Performance bonds prior to Advance Payment to the subcontractor. C.04 Analyzing variation from subcontractors and onward submission to Engineer. C.05 Quantification for Re-measured Subcontractors. D Material Requests. D.01 Forwarding Timely Material Requests as per the Instruction by Project Manager. E Value Engineering. E.01 Value Engineering to reduce Contractor's risks for Certain items within the Contract (Time related / Cost Related). F Correspondance Letters F.01 Related Commercial Correspondance letters to the Engineer. F.02 Related Commercial Correspondance letters to the Subcontractors. G Cost Monitoring Cash Flow Charts. G.01 Submitting Monthly Provision for Payments to the Subcontractors (For Head Office Commercial Team). G.02 Submitting Monthly Main Contractor's Payment Approval Status Log (For Head Office Commercial Team). G.03 Submitting Monthly Main Contractor Variation's Log (For Head Office Commercial Team).
-
-
Quantity Surveyor (Avani Palm View Dubai Hotel & Suites - Dubai, U.A.E)
-
May 2018 - Jul 2021
Dubai, United Arab Emirates A Monthly Payment Application (IPA). A.01 Work Progress Break down as per Original Contract. A.02 Work Progress Break down as per issued VO's. A.03 Work Progress Break down for Variation on Account (items under approval without VO from Engineer/Employer). A.04 Material On Site as per the Contract. A.05 Follow Up with Engineer till IPC is issued. B Variations. B.01 Submitting timely Notices as per Contract B.02 Submitting Particular details to the Engineer and further… Show more A Monthly Payment Application (IPA). A.01 Work Progress Break down as per Original Contract. A.02 Work Progress Break down as per issued VO's. A.03 Work Progress Break down for Variation on Account (items under approval without VO from Engineer/Employer). A.04 Material On Site as per the Contract. A.05 Follow Up with Engineer till IPC is issued. B Variations. B.01 Submitting timely Notices as per Contract B.02 Submitting Particular details to the Engineer and further follow-ups till VO is issued. B.03 Preparation of Potential Variation Schedule for Employer's information to know overall Expected final Contract Value. C Sub Contractor Payments. C.01 Certifying monthly payments to the Subcontractors as per Subcontract agreement. C.02 Tracking back charges to the subcontractors as per their scope of work and also from the construction team. C.03 Follow up with Advance Payment guarantee and Performance bonds prior to Advance Payment to the subcontractor. C.04 Analyzing variation from subcontractors and onward submission to Engineer. C.05 Quantification for Re-measured Subcontractors. D Material Requests. D.01 Forwarding Timely Material Requests as per the Instruction by Project Manager. E Value Engineering. E.01 Value Engineering to reduce Contractor's risks for Certain items within the Contract (Time related / Cost Related). F Correspondance Letters F.01 Related Commercial Correspondance letters to the Engineer. F.02 Related Commercial Correspondance letters to the Subcontractors. G Cost Monitoring Cash Flow Charts. G.01 Submitting Monthly Provision for Payments to the Subcontractors (For Head Office Commercial Team). G.02 Submitting Monthly Main Contractor's Payment Approval Status Log (For Head Office Commercial Team). G.03 Submitting Monthly Main Contractor Variation's Log (For Head Office Commercial Team).
-
-
Quantity Surveyor (Royal M Hotel & Resort - Abu Dhabi, U.A.E).
-
Mar 2017 - Apr 2018
Abu Dhabi, United Arab Emirates Prepare and Process monthly valuation under the main Contract agreement and follow up with Client and Consultant QS for Payment Certificate. Liase with Commercial manager in ensuring proper and timely notices are given under the relevant clauses of main Contract. Identify and process variations to Engineer / Consultant including variation orders quantification and Evaluation. Preparation of Full Commercial reports for Presentation.
-
-
-
Al Sarh Contracting L.L.C.
-
United Arab Emirates
-
Construction
-
1 - 100 Employee
-
Quantity Surveyor (Syan Park-1, Arjan - Dubai, U.A.E).
-
Nov 2014 - Dec 2016
Dubai, United Arab Emirates • Evaluate and reviewing subcontractors interim payments with their site progress and issuing payment certificate / response accordingly • Taking site measurements and quantity take offs for payments, variations • Monitoring quantities for cost controlling, maintain records of site measurements and quantities • Calculation of interim and final quantities. • Preparation of internal (company) subcontractor salaries according to their work progress and productivity with company… Show more • Evaluate and reviewing subcontractors interim payments with their site progress and issuing payment certificate / response accordingly • Taking site measurements and quantity take offs for payments, variations • Monitoring quantities for cost controlling, maintain records of site measurements and quantities • Calculation of interim and final quantities. • Preparation of internal (company) subcontractor salaries according to their work progress and productivity with company approved rates. • Taking Quotes from subcontractors and finalizing the subcontractor. • Familiar with POMI and standard methods of measurement • Knowledge in FIDIC conditions of contract related to Payments Show less
-
-
-
Apollo Builders Pvt Ltd.
-
India
-
Real Estate
-
1 - 100 Employee
-
Civil Site Engineer (Apollo Oasis, Kerala. India)
-
Jul 2012 - Jul 2014
Calicut Area, India • Acting as the technical advisor for the Project • Checking drawings and quantities for accuracy of calculations and work. • Ensuring that all materials used and work performed are as specifications • Overseeing the selection and requisition of materials • Preparing daily report of site work for the Project Manager. • Meet with clients, subcontractors, suppliers, as required • Giving purchase order of material for the project. • Work to ensure schedules are kept and… Show more • Acting as the technical advisor for the Project • Checking drawings and quantities for accuracy of calculations and work. • Ensuring that all materials used and work performed are as specifications • Overseeing the selection and requisition of materials • Preparing daily report of site work for the Project Manager. • Meet with clients, subcontractors, suppliers, as required • Giving purchase order of material for the project. • Work to ensure schedules are kept and jobs are being completed on time. • Preparing M book for making bill to contractor. • Ensuring that all materials used and work performed are as specifications. • Day to Day management of site including supervision and monitoring site labour force and the safety at site. • Inspect work areas regularly for potential hazards and rectify,so as to maintain a safe environment • Report and assist in the investigation of safety violations, dangerous occurrence and accidents at site where necessary. • Undertake additional tasks and responsibilities as and when required or instructed. • On site decision making Time management – deciding who leaves the job site, who picks up material, who assists the supervisor Show less
-
-
Education
-
Mahatma Gandhi University
Bachelor’s Degree, Civil Engineering