Galih Budiarto
Kacper ia a good person, i had very nice experience with him in the PLTMG 10 MW Project. Kacper has been helpful and effective his specific task as Civil Engineers. Friendly, enthusiastic, energethic.
Ian Marsden
I worked with Kacper while build a new quick fire power generation plant in the UK. I was managing the mechanical installation of the plant which in-turn required close co-ordination with the structural build of the plant, Kacper was managing the structural build. Kacper was a very knowledgeable, helpful and integral part of the team which made the project run very smoothly. We had many obstacles to overcome during the build and all trades worked very well together! Nothing was ever a issue for Kacper, going above and beyond his contractual remit in times to ensure that the project always came first. I would have no hesitation in offering a reference for Kacper for any future employment he should wish to for take.
Galih Budiarto
Kacper ia a good person, i had very nice experience with him in the PLTMG 10 MW Project. Kacper has been helpful and effective his specific task as Civil Engineers. Friendly, enthusiastic, energethic.
Ian Marsden
I worked with Kacper while build a new quick fire power generation plant in the UK. I was managing the mechanical installation of the plant which in-turn required close co-ordination with the structural build of the plant, Kacper was managing the structural build. Kacper was a very knowledgeable, helpful and integral part of the team which made the project run very smoothly. We had many obstacles to overcome during the build and all trades worked very well together! Nothing was ever a issue for Kacper, going above and beyond his contractual remit in times to ensure that the project always came first. I would have no hesitation in offering a reference for Kacper for any future employment he should wish to for take.
Galih Budiarto
Kacper ia a good person, i had very nice experience with him in the PLTMG 10 MW Project. Kacper has been helpful and effective his specific task as Civil Engineers. Friendly, enthusiastic, energethic.
Ian Marsden
I worked with Kacper while build a new quick fire power generation plant in the UK. I was managing the mechanical installation of the plant which in-turn required close co-ordination with the structural build of the plant, Kacper was managing the structural build. Kacper was a very knowledgeable, helpful and integral part of the team which made the project run very smoothly. We had many obstacles to overcome during the build and all trades worked very well together! Nothing was ever a issue for Kacper, going above and beyond his contractual remit in times to ensure that the project always came first. I would have no hesitation in offering a reference for Kacper for any future employment he should wish to for take.
Galih Budiarto
Kacper ia a good person, i had very nice experience with him in the PLTMG 10 MW Project. Kacper has been helpful and effective his specific task as Civil Engineers. Friendly, enthusiastic, energethic.
Ian Marsden
I worked with Kacper while build a new quick fire power generation plant in the UK. I was managing the mechanical installation of the plant which in-turn required close co-ordination with the structural build of the plant, Kacper was managing the structural build. Kacper was a very knowledgeable, helpful and integral part of the team which made the project run very smoothly. We had many obstacles to overcome during the build and all trades worked very well together! Nothing was ever a issue for Kacper, going above and beyond his contractual remit in times to ensure that the project always came first. I would have no hesitation in offering a reference for Kacper for any future employment he should wish to for take.
0
/5.0 / Based on 0 ratingsFilter reviews by:
Credentials
-
European Engineer EUR ING
FEANIJun, 2020- Sep, 2024 -
The building license in speciality of structure and construction
Polska Izba Inżynierów BudownictwaDec, 2019- Sep, 2024 -
Certified Member (CM)
Association of Polish Engineers in Great BritainOct, 2019- Sep, 2024 -
Layher Scaffold in practice
Layher, Inc.Feb, 2017- Sep, 2024 -
MS Project
PC Open Sp. z o.o.Nov, 2015- Sep, 2024 -
CAD Engineer
AutodeskApr, 2015- Sep, 2024 -
Site Supervisor Safety Training Scheme
CITBJul, 2017- Sep, 2024 -
G2 Operation of equipment, installations and networks in a supervisory capacity
Stowarzyszenie Polskich EnergetykówJun, 2017- Sep, 2024 -
G2 Operation of equipment, installations and networks in an operational capacity
Stowarzyszenie Polskich EnergetykówJun, 2017- Sep, 2024 -
Pre-Medical First Aid Training
BHP Center sp. z o. o.Dec, 2018- Sep, 2024
Experience
-
Tekniq Oy
-
Finland
-
Business Consulting and Services
-
1 - 100 Employee
-
Civil Construction Supervisor
-
Oct 2018 - Present
Project supervision and consultation for Wärtsilä Energy Power Plants Construction works execution in EPC formula - 90MW (electrical) and 84MW (district heating output) Combined heat and power (CHP) Plant in Dresden, Germany Investor - DREWAG Principal contractor - Wärtsilä Deutschland GmbH Technical Advisory for the Owner - 19MW Boost Capacity (Phase 2 - Extension) of Gas Power Plant in Borg El Arab, Egypt Investor - Kharaba Egypt Kuwait Holdings (EKH) Group Principal contractor - EL-Nour, Wärtsilä EEQ (Engineering & Equipment) Civil works supervision - 10MW Multiple-fuel Power Plant in Nabire, Papua, Indonesia Investor - Indonesia Power Principal contractor - PT.PP (Persero) Ptk, Wärtsilä EEQ (Engineering & Equipment)
-
-
-
MKL BAU sp. z o.o.
-
Poland
-
Construction
-
1 - 100 Employee
-
Project Manager
-
Jan 2018 - Sep 2018
Civil works execution - 34 MW Avonmouth Energy Recovery Facility in Bristol, United KingdomInvestor - ViridorPrincipal contractor - CNIM S.A. and Clugston Construction LtdCivil works execution - 100MW Gas Power Plant in Mainz, GermanyInvestor - Kraftwerke Mainz-WiesbadenPrincipal contractor - Wärtsilä Energy Power PlantsCivil works execution - 50MW Gas Power Plant in Peterborough, United KingdomInvestor - Centrica plcPrincipal contractor - Wärtsilä Energy Power Plants
-
-
Civil Engineer
-
Jun 2017 - Dec 2017
Civil works execution - 50MW Gas Power Plant in Peterborough, United KingdomInvestor - Centrica plcPrincipal contractor - Wärtsilä Energy Power Plants
-
-
-
Almont Group
-
United Kingdom
-
Travel Arrangements
-
1 - 100 Employee
-
Designer / Civil Engineer
-
Nov 2016 - May 2017
Design and execution control of scaffolds on site - 910MW Coal-fired Power Plant in Jaworzno, Poland Investor - Tauron Wytwarzanie S.A. Principal contractor - Rafako S.A. Design and execution control of scaffolds on site - 910MW Coal-fired Power Plant in Jaworzno, Poland Investor - Tauron Wytwarzanie S.A. Principal contractor - Rafako S.A.
-
-
-
Bilfinger
-
Germany
-
Mechanical Or Industrial Engineering
-
700 & Above Employee
-
Designer / Civil Engineer
-
Mar 2016 - Oct 2016
Design and execution control of scaffolds on site - 1075MW Coal-fired Power Plant in Kozienice, Poland Investor - Enea Wytwarzanie S.A. Principal contractor - Consortium Polimex Mostostal & Mitsubishi Hitachi Power Systems Design and execution control of scaffolds on site - 1075MW Coal-fired Power Plant in Kozienice, Poland Investor - Enea Wytwarzanie S.A. Principal contractor - Consortium Polimex Mostostal & Mitsubishi Hitachi Power Systems
-
-
Education
-
Łódź University of Technology
Master of Science, Civil engineering - constructions -
Łódź University of Technology
Engineer, Civil engineering - constructions