Kaan Mert ENGİN
Survey and Infrastructure Group Chief at Kalyon Construction Group- Claim this Profile
Click to upgrade to our gold package
for the full feature experience.
Topline Score
Bio
Experience
-
Kalyon Construction Group
-
Türkiye
-
Construction
-
400 - 500 Employee
-
Survey and Infrastructure Group Chief
-
Jul 2023 - Present
Toscana Valley Concept Villa Project Main Contractor: Kalyon Construction Group & Özyazıcı Construction JV Project Budget: $ 300 M Total Area : 445935 sqm -I am responsible for all survey and infrastructures works of 357 villas, roads and infrastructure in preparing stake out data, earthwork volume calculations and progress payment reports in the site, creating work program and managing subcontractors, ensuring coordination with design, mep and architectural teams. Toscana Valley Concept Villa Project Main Contractor: Kalyon Construction Group & Özyazıcı Construction JV Project Budget: $ 300 M Total Area : 445935 sqm -I am responsible for all survey and infrastructures works of 357 villas, roads and infrastructure in preparing stake out data, earthwork volume calculations and progress payment reports in the site, creating work program and managing subcontractors, ensuring coordination with design, mep and architectural teams.
-
-
-
Sera Group - Sera Construction
-
Türkiye
-
Construction
-
100 - 200 Employee
-
Survey and Infrastructure Group Chief
-
May 2023 - Jul 2023
Malatya 800 Earthquake Houses, Roads and Infrastructures Project Main Contractor: Sera Group Project Budget: $ 100 M -I was responsible for all survey and infrastructures works of 800 earthquake houses, roads and infrastructure. Malatya 800 Earthquake Houses, Roads and Infrastructures Project Main Contractor: Sera Group Project Budget: $ 100 M -I was responsible for all survey and infrastructures works of 800 earthquake houses, roads and infrastructure.
-
-
-
Limak Group of Companies
-
Türkiye
-
Civil Engineering
-
700 & Above Employee
-
Survey Group Chief
-
May 2021 - May 2023
Kuwait International Terminal Building & Car Park Project - KUWAIT- Main Contractor: Limak Construction- Design: Fosters & Partners, AECOM- Consultant: Gulf-KEO- Project Budget: ($5.5 billion)- Capacity 25 million passengers- Total Construction Area: 1.150.000 sqmKuwait International Terminal Building & Car Park Construction (Excavation-Concrete Work-Shell Cassette Roof-Façade-Steel Work-Precast-Special Airport System-Architectural Work) + Car Park Building (Roof) + All Infrastructure Work + Landscape Works + Terminal Roads) Coordination, preparation stake out data and implementation of projects, submission and approval of all work to the (Gulf-Keo) consultant In all the parts Show less
-
-
Survey Engineer
-
Aug 2017 - May 2021
Kuwait International Airport Terminal 2 Project
-
-
-
EKOL HARİTA VE MÜHENDİSLİK TİC. LTD. ŞTİ
-
Çanakkale, Çanakkale, Türkiye
-
Survey Engineer
-
Jul 2016 - May 2017
Akcansa Mine Survey Works(Current map production, earthwork volume calculations and other survey works.) Akcansa Mine Survey Works(Current map production, earthwork volume calculations and other survey works.)
-
-
Education
-
Yıldız Teknik Üniversitesi
Bachelor of Engineering - BE, Survey Engineering