Jimmy Sanjaya

Chief Operating Officer at PT Makadia Jaya Perkasa
  • Claim this Profile
Contact Information
us****@****om
(386) 825-5501
Location
Jakarta, Jakarta, Indonesia, ID

Topline Score

Topline score feature will be out soon.

Bio

Generated by
Topline AI

You need to have a working account to view this content.
You need to have a working account to view this content.

Experience

    • Indonesia
    • Construction
    • 1 - 100 Employee
    • Chief Operating Officer
      • Feb 2018 - Present

    • Indonesia
    • Oil and Gas
    • 700 & Above Employee
    • Pre-commissioning Area Leader
      • Oct 2017 - Present

      Responsible in planning, budgeting, and executing the pre-commissioning activities at Gas Processing Facility Area of Jambaran-Tiung Biru Project, including the interface with construction and commissioning team.With construction division, leading the team in implementing digitization in construction-commissioning activity, utilizing RFID technology to minimize idle time, unsafe condition, and time discrepancy in managerial decision-making.

    • Construction & Pre-commissioning Engineer
      • Mar 2017 - Sep 2017

      Responsible in planning, scheduling, and budgeting of pre-commissioning activity for PT Rekayasa Industri bidding proposal.

    • Pre-commissioning & Commissioning Engineer
      • May 2015 - Mar 2017

      In charge of highly challenging jobs from lube oil flushing, steam blowing, turbines-compressors mechanical run test, ammonia catalyst reduction and activation, to completing the final performance test.Manage 50 crews under 4 supervisors, able to achieve excellent plant operating quality. Also reducing lube oil flushing duration up to 60% using innovative procedure.

    • Indonesia
    • Business Consulting and Services
    • 300 - 400 Employee
    • Process Engineer
      • Jul 2013 - Nov 2014

      Lead a team of process engineers to build the ethylene plant computer simulation using Aspen HYSYS, aiding the revamping plan of PT Chandra Asri Petrochemical. Also, part of a team to perform feasibility study on Indonesia’s Ministry of Industry plan to built 5.000 MTPD Methanol Plant and downstream industries in Teluk Bintuni, Irian Jaya. Lead a team of process engineers to build the ethylene plant computer simulation using Aspen HYSYS, aiding the revamping plan of PT Chandra Asri Petrochemical. Also, part of a team to perform feasibility study on Indonesia’s Ministry of Industry plan to built 5.000 MTPD Methanol Plant and downstream industries in Teluk Bintuni, Irian Jaya.