Oji Fibre Solutions
-
New Zealand
-
Paper and Forest Product Manufacturing
-
400 - 500 Employee
-
Electrical/Instrumentation Maintenance Engineer
-
Jan 2019 - Present
E/I Maintenance engineer E/I Maintenance engineer
-
-
-
Vale
-
Brazil
-
Mining
-
700 & Above Employee
-
-
Jan 2008 - Dec 2018
I was involved in the full project management, design, procurement, construction and comissioning processes from capital appropriation request preparation to project handoverSome major projects I have worked on include:1. Larona LGS1 and LGS2 85MVA upgrades - generator, excitation, protection and automation. (Jan 2008- May 2012)2. Furnace 1 Power Demand Stabilization US$24.8M (Oct 2012 - Sept 2013)3. Kiln #4 VFD (variable frequency drive) upgrade YS$2.0M (2009 -2011)4. Sorowako Hospital Upgrade (2008-2009)5. 2 x12.7MW electric boiler upgrade US$11M - FEL3 and basic engineering.6. 150kV GIS (gas insulated switch gear) upgrade - FEL2 study7. Technical reviews of other capital projects.8. Coal transportation project at Balantang US$17.5M (Sept 2014 till Dec 2015)9. Furnace #4 Electrode Stability project US$43.0M (June 2014 till present). Show less
-
-
-
Jan 2005 - Jan 2008
-
-
-
Pavilion Technologies
-
United States
-
Software Development
-
1 - 100 Employee
-
Systems Engineer - Site Consultant
-
Jul 2004 - Dec 2004
I spent the first 3 months completing detailed design for the Norske Skog Albury Recycled Fibre plant automation upgrade to a Metso automation system. This project was cancelled due to capital cost reductions. I moved to a plant maintenance support engineer role that followed up on shift report logs. I was in this role for 3 months. I spent the first 3 months completing detailed design for the Norske Skog Albury Recycled Fibre plant automation upgrade to a Metso automation system. This project was cancelled due to capital cost reductions. I moved to a plant maintenance support engineer role that followed up on shift report logs. I was in this role for 3 months.
-
-
-
Glatfelter
-
United States
-
Manufacturing
-
700 & Above Employee
-
Project Engineer
-
Dec 2002 - Jun 2004
I was the project engineer responsible for planning the refurbishment and upgrading of a manila batch digester plant. This project involved modifying the stock control and wet lap washing machine to feed a screw press to produced dried pulp for transport. This was an extremely hands-on role due to the limited budget of GBP 250,000. Due to this budget constraint, I was responsible for the following tasks: 1. All project technical planning, budget and schedule management. 2. PLC programming of Modicon PLC. 3. Process design of back end (digester pulp washing) system. 4. Mechanical supervision. 5. Electrical design and wiring. 6. Civil construction planning and supervision. 7. All procurement for all disciplines. After this was complete - I worked on a water treatment plant upgrade to add automation and monitoring equipment to the existing plant. Equipment commissioning Show less
-
-
-
Norske Skog
-
Norway
-
Paper and Forest Product Manufacturing
-
700 & Above Employee
-
Maintenance Engineer
-
1997 - 2002
Developing electrical and control system preventative maintenance routines. Capital project design reviews. Shutdown startup cover Project Planning and commissioning Developing electrical and control system preventative maintenance routines. Capital project design reviews. Shutdown startup cover Project Planning and commissioning
-
-
Education
-
University of Canterbury
Bachelor of Engineering (Hons) (Electrical and Electronic), Electrical and Electronics Engineering