Halil İSPİR
" Ferhat and I worked together during the construction process of the Alpaslan 2 dam and HEPP project, which are one of the most important projects in Turkey. Ferhat was working as a Civil Engineer. He is a successful friend who is knowledgeable and open to learning, adapts to teamwork and fulfills his duties responsibly.
Martin Tichy
i worked with Ferhat on Alpaslan 2 dam and HPP project.he is a hard worker with good experience,he would be a good asset for any company.
Halil İSPİR
" Ferhat and I worked together during the construction process of the Alpaslan 2 dam and HEPP project, which are one of the most important projects in Turkey. Ferhat was working as a Civil Engineer. He is a successful friend who is knowledgeable and open to learning, adapts to teamwork and fulfills his duties responsibly.
Martin Tichy
i worked with Ferhat on Alpaslan 2 dam and HPP project.he is a hard worker with good experience,he would be a good asset for any company.
Halil İSPİR
" Ferhat and I worked together during the construction process of the Alpaslan 2 dam and HEPP project, which are one of the most important projects in Turkey. Ferhat was working as a Civil Engineer. He is a successful friend who is knowledgeable and open to learning, adapts to teamwork and fulfills his duties responsibly.
Martin Tichy
i worked with Ferhat on Alpaslan 2 dam and HPP project.he is a hard worker with good experience,he would be a good asset for any company.
Halil İSPİR
" Ferhat and I worked together during the construction process of the Alpaslan 2 dam and HEPP project, which are one of the most important projects in Turkey. Ferhat was working as a Civil Engineer. He is a successful friend who is knowledgeable and open to learning, adapts to teamwork and fulfills his duties responsibly.
Martin Tichy
i worked with Ferhat on Alpaslan 2 dam and HPP project.he is a hard worker with good experience,he would be a good asset for any company.
Credentials
-
Autodesk Civil 3D 2021 Essential Training
LinkedInJan, 2022- Nov, 2024 -
Construction Industry: Productivity
LinkedInNov, 2021- Nov, 2024 -
Construction Management: Introduction to Lean Construction
LinkedInNov, 2021- Nov, 2024 -
First Aid
Türkiye Cumhuriyeti Millî Eğitim BakanlığıJan, 2016- Nov, 2024
Experience
-
Cevahir Yapi
-
Türkiye
-
Construction
-
1 - 100 Employee
-
Civil Engineer
-
May 2023 - Present
-
-
-
Facility Clean Service GmbH
-
Mannheim, Baden-Württemberg, Germany
-
Service Manager
-
Dec 2022 - May 2023
200 km fiber infrastructure renovation work in Baden-Württemberg, Germany. 200 km fiber infrastructure renovation work in Baden-Württemberg, Germany.
-
-
-
Arban Elektirik Üretim A.Ş.
-
Construction
-
Construction Manager
-
Mar 2021 - Dec 2022
The name of the project is Direktas Regulator and HEPP ( 7.7 MWm). The project consists of regulator, transmission tunnel, transmission line and powerhouse. The regulator consists of a water intake structure, a settling basin, a spillway, a fishway and a gravel passage. With the help of a regulator (from 1071 m elevation), the water is conveyed to the transmission tunnel (7% inclination and 4x4 dimensions) then the water passes through the GRP pipe (1240 m long) which is resistant to 12 bar pressure, after that the water arrives the Steel penstock (60 m long). Finally, it is transmitted to the powerhouse where the three vertical Francis turbines are located (The Elevation of the powerhouse is 940 meters). 85% of the project has been completed Show less
-
-
-
ENERGO-PRO
-
Czechia
-
Utilities
-
200 - 300 Employee
-
Concrete Works Engineer
-
Dec 2019 - Dec 2020
The name of the project is Alpaslan 2 Dam and HEPP ( 280 MWm).The project consists of Viaduct, Spillway, Water Intake Structure, Switchyard, Shaft Chimneys, stilling basin, grouting gallery, Powerhouse, Tailwater, concrete shear wall, Road and retaining walls.
-
-
Road and Resettlement Engineer
-
Sep 2019 - Dec 2019
When the project was completed 5 villages would have been flooded by the dam. I was responsible for the resettlement. The project consists of 240 houses, 30 official public buildings, waterline and reservoir, sewerage system, road, pavement, electricity line and stone-wall.
-
-
-
my own business
-
Design Services
-
1 - 100 Employee
-
Civil Engineer
-
Jun 2019 - Sep 2019
-
-
-
Yumutgan Mühendislik
-
Adıyaman, Türkiye
-
Civil Engineering Intern
-
Jan 2019 - Jun 2019
I Worked as an Intern Civil Engineer in the School Project of the Directorate of National Education of Adıyaman Province, which was commissioned by the European Union. I Worked as an Intern Civil Engineer in the School Project of the Directorate of National Education of Adıyaman Province, which was commissioned by the European Union.
-
-
-
Cafer Oğulları İnş. LTD. ŞTİ
-
Adiyaman, Turkey
-
Civil Technician
-
Oct 2013 - Dec 2014
I dealt with the auditing of contractors and official documents that built my clients homes. I dealt with the auditing of contractors and official documents that built my clients homes.
-
-
-
TPAO
-
Türkiye
-
Retail
-
1 - 100 Employee
-
Construction Technician Intern
-
Jul 2013 - Sep 2013
I worked as a trainee construction technician in the construction of Cendere-1-2 and 3 Oil Drilling Locations in TPAO Adıyaman Region. I worked as a trainee construction technician in the construction of Cendere-1-2 and 3 Oil Drilling Locations in TPAO Adıyaman Region.
-
-
Education
-
Adıyaman Üniversitesi
Bachelor's degree, Civil Engineering -
Anadolu Üniversitesi
Bachelor's degree, Faculty of Business Administration -
Kahramanmaraş Sütçüimam Üniversitesi
Associate's degree, Construction Technology