Fawwaz Mahmood
QA/QC Engineer at Impian Tekad Sdn Bhd- Claim this Profile
Click to upgrade to our gold package
for the full feature experience.
Topline Score
Bio
Experience
-
Impian Tekad Sdn Bhd
-
Malaysia
-
Construction
-
1 - 100 Employee
-
QA/QC Engineer
-
Jul 2017 - Present
Project: Jimah East Power 2x1000MW Coal Fired Power Plant – Negeri Sembilan• Involved in Mechanical erection & Insulation works. • Execute QA/QC team work plans according to the project scopes and based on the QA/QC specifications and requirements.• Preparing Inspection Test Plans (ITP) and documentations for QA/QC activities.• Organizing inspections test / check / walk down / site coordination’s with others department such as Erection Team, and others representatives for witnessing inspection and recording.• Request and advise client for any site inspection as per ITP requirements.• Ensure that the requirements of ITP (Inspection & Test Plan) are performed correctly.• Verify closing punch list and carry out inspection on material verification.• Mark-up drawing for progress specifications. Show less
-
-
QA/QC Engineer
-
Dec 2016 - Jul 2017
Project: Pengerang Cogeneration Plant - Johor• Involved in Mechanical and Piping erection works for water treatment plant.• Execute QA/QC team work plans according to the project scopes and based on the QA/QC specifications and requirements.• Preparing Inspection Test Plans (ITP), Test Package for piping system and documentations for QA/QC activities.• Organizing inspections test / check / walk down / site coordination’s with others department such as Erection Team, and others representatives for witnessing inspection and recording.• Request and advise client for any site inspection as per ITP requirements.• Ensure that the requirements of ITP (Inspection & Test Plan) are performed correctly.• Conduct hydrostatic test, pneumatic test and mechanical test.• Verify closing punch list and carry out inspection on material verification.• Mark-up drawing for progress specifications. Show less
-
-
Site Engineer
-
Jun 2015 - Dec 2016
Project: Brunei Liquefied Natural Gas (BLNG) – COGEN II, Brunei Darussalam.• Involved in Electrical and Instrumentation erection works.• Lead and execute cable pulling and cable termination team work plans according to project scopes.• Conduct daily toolbox meeting and monitor work progress of cable pulling and cable termination team members.• Liaising with client and other contractor for problem solving situation.• Keep track of work progress and preparing daily reports. • Responsible for allocating manpower.• Permit-to-work coordination.• Supervise site work execution in compliance of official document/specification and safety requirement. • Heavily involved in supervision of cable installation. • Installation of High Voltage (HV), Medium Voltage (MV), Low Voltage (LV), and Control cables.• Supply, laying, termination and testing of Power and Control cables for:- GIS 66kV Switch House 11/66kV Transformer Gas Turbine Generator (GTG) GTG Auxiliary Transformer. Local Control Cabin (LCC) 11kV Generator Circuit Breaker (GCB) 66kV/34.5kV Step-down Transformer 11kV Distribution / Starter Motor Transformer 11kV Switchboard 415V Switchboard Waste Heat Boiler(WHB) Show less
-
-
Education
-
Universiti Kuala Lumpur
Bachelor of Engineering - BE, Electrical and Electronics Engineering -
Universiti Kuala Lumpur
Diploma, Marine Electrical & Electronic Engineering