    • Saudi Arabia
    • Chemical Manufacturing
    • 1 - 100 Employee
    • Planning & Scheduling Lead
      • Nov 2021 - Present

      Al Khobar, Eastern, Saudi Arabia Working as a Regional Planning & Scheduling Lead for Portfolio of projects in Middle East, Egypt and Turkey region. The mega EPCs Projects include Green / Blue Hydrogen Production Plants, Ammonia (NH3) Plants, Air Separation Units (ASU), Solar and Wind Power Plants etc. The role and responsibilities include Project Planning & Scheduling, Schedule Delay Analysis, Progress Monitoring, Cost Controls, Estimation etc. as required for the ongoing and upcoming projects.

    • Saudi Arabia
    • Oil and Gas
    • 700 & Above Employee
    • Scheduling Engineer - Project Management Team (SAPMT)
      • Nov 2019 - Nov 2021

      Al-Khobar Governorate, Saudi Arabia Worked with Saudi Aramco Project Management Team on Gas Compression Plants Pipelines in Haradh and Hawiyah field, as a part of the Field Gas Compression Projects .The project scope of work includes a combination of greenfield and brownfield work within large and remote geographic operating area. Project scope comprises installation of certein flowlines ,trunk lines and transmission lines together with associated facilities such as Remote Headers , Off-Plot tie in facilities (OPTFs) , Gas… Show more Worked with Saudi Aramco Project Management Team on Gas Compression Plants Pipelines in Haradh and Hawiyah field, as a part of the Field Gas Compression Projects .The project scope of work includes a combination of greenfield and brownfield work within large and remote geographic operating area. Project scope comprises installation of certein flowlines ,trunk lines and transmission lines together with associated facilities such as Remote Headers , Off-Plot tie in facilities (OPTFs) , Gas gathering manifolds (GGMs) and Gas compression plants (GCPs). Show less

    • Saudi Arabia
    • Construction
    • 700 & Above Employee
    • Project Controls Manager - PMOD
      • Sep 2017 - Sep 2019

      Saudi Arabia Working for Corporate Office by leading multiple mega pipeline projects (Master Gas System, Phase II, Fadhili Downstream Pipeline and Mazalij & Abu Jifan Pipelines). Projects scope comprises installation of new cross country gas/crude pipelines (56”, 46”, 24” & 18” dia) from Western Region to Eastern Region connecting to Central Region of Saudi Arabia. Program consists LSTK Engineering, Procurement & Construction (EPC) contract with a value of US$ 2.15 Billiion with a total length of 1,354KMS.… Show more Working for Corporate Office by leading multiple mega pipeline projects (Master Gas System, Phase II, Fadhili Downstream Pipeline and Mazalij & Abu Jifan Pipelines). Projects scope comprises installation of new cross country gas/crude pipelines (56”, 46”, 24” & 18” dia) from Western Region to Eastern Region connecting to Central Region of Saudi Arabia. Program consists LSTK Engineering, Procurement & Construction (EPC) contract with a value of US$ 2.15 Billiion with a total length of 1,354KMS. • Develops required policies, procedures and processes flows for the Project Control function to maintain efficient operational excellence. • Develops resource loaded integrated master EPC schedule in Primavera P6 /V17) with its components like basis of schedule, reporting formats, manpower histograms, early & late S curves. • Providing expert advice on project controls issues related to current projects and lesson learned to project controls director. Conducting analysis of actual performance against plan. • Supervising a team of planners across all projects responsible for tracking schedules and preparing required reports on daily /weekly/monthly. • Monitoring regularly detailed construction progress of the project to ensure full adherence to work plans within the agreed time ,budget and resources. Notifying project managers of any under or over-run on project schedule ,costs, recommending courses of action and coordinating progress . • Integrate planning, budgeting and cost analysis reports to develop a comprehensive overview of performance to date and to determine future approach. • Responsible for the forecast project completion costs based on trends including productivity measurements, labour rate analysis, commitments, management of change, schedule impacts, material cost variance, contract changes, and invoice payments.

    • Lead Project Controls Engineer
      • Sep 2015 - Aug 2017

      Al-Khobar Governorate, Saudi Arabia

    • United Kingdom
    • Industrial Machinery Manufacturing
    • 1 - 100 Employee
    • Planning & Scheduling Engineer
      • Mar 2013 - Jun 2015

      Qatar Petroleum ,Qatar Gas ,Qatar Fuel Additive Company ,Laffan Refinery • Develop, implement & maintain the project controls procedure, project schedules (level 1-4), and reporting systems specific to project. Provide guidance to the project control team working for the project. • Develop resource loaded integrated master EPC schedule in Primavera P6 /V17) with its components like basis of schedule, reporting formats, manpower histograms, early & late S curves. • Co-ordination with engineering, procurement and construction teams for routine planning… Show more • Develop, implement & maintain the project controls procedure, project schedules (level 1-4), and reporting systems specific to project. Provide guidance to the project control team working for the project. • Develop resource loaded integrated master EPC schedule in Primavera P6 /V17) with its components like basis of schedule, reporting formats, manpower histograms, early & late S curves. • Co-ordination with engineering, procurement and construction teams for routine planning activities and preparation of reports. • Responsible for the forecast project completion costs based on trends including productivity measurements, labour rate analysis, commitments, management of change, schedule impacts, material cost variance, contract changes, and invoice payments. • Integrate planning, budgeting and cost analysis reports to develop a comprehensive overview of performance to date and to determine future approach. • Review and analyse all scheduling reports and forecasts against plan, studying and assessing trends and fluctuations providing clear interpretation and advice on suggested appropriate action to relevant project management. • Developed L4 schedule for Turnarounds & monitored those using Primavera P6 with all its associated sub plans . • Coordinate the development of the turnaround work scope received from all departments such as operations, inspection, projects, and maintenance. • Ensure work scope justification and compliance with the turnaround work scope criteria. • Field review scope of work and develop job steps and requirements for craft and man hours for each submitted work request . Show less

    • Planning Engineer
      • Jan 2012 - Feb 2013

      Neelum Jhelum Project (Thermal power plant of capacity 12 MW) • Develop & update various project monitoring packages via level 3 schedules, progress measurement system, project reporting systems and invoicing systems etc. • Assimilate scope of work and conceive the project in terms of schedule. • Assist engineering & procurement disciplines in preparing micro schedule for technical document register deliverables & procurement tracking register milestones schedules and provide input as required. Prepare the construction activities schedule in… Show more • Develop & update various project monitoring packages via level 3 schedules, progress measurement system, project reporting systems and invoicing systems etc. • Assimilate scope of work and conceive the project in terms of schedule. • Assist engineering & procurement disciplines in preparing micro schedule for technical document register deliverables & procurement tracking register milestones schedules and provide input as required. Prepare the construction activities schedule in consultation with the construction team • Timely issue of quality project planning deliverables & progress reports. • Monitor the work in progress with respect to the approved schedules/milestones and prepare weekly/ monthly progress reports. • Prepare issues and Action Item register and keep update. • Prepare Communication Plan and Distribution Plan on Project and keep update of communication list. • Review proposals from subcontractors on project execution and schedule. • Keep PCM & Lead planning engineer appraised of the status/ constraints. • Responsible for preparation and updating the commodity release plan/ curve. • Identify and communicate potential schedule constraints to proposal team to ensure bid clarifications. • Analyze and communicate to the Lead project control engineer/ Project Manager on observation of any instance across disciplines for any major variance between the actual work in progress and the approved schedules. • Post award review the contract for schedule and commercial parameters to validate/ compare with the original submitted documents. Show less

    • Planning Engineer
      • Jan 2011 - Dec 2011

      Nishat Chunian Power LTD . (NCPL ) • Develop resource loaded integrated master EPC schedule in Primavera P6 /V17) with its components like basis of schedule, reporting formats, manpower histograms, early & late S curves. • Preparation and maintenance of Schedule/Resource/Cost S curves. • Planning, tracking and achieving Project KPIs & performance in line with Company’s asset working program. • Prepare and publish the Area Maintenance Look Ahead schedules and facilitate Look Ahead and Daily Planning meetings. • Ensure… Show more • Develop resource loaded integrated master EPC schedule in Primavera P6 /V17) with its components like basis of schedule, reporting formats, manpower histograms, early & late S curves. • Preparation and maintenance of Schedule/Resource/Cost S curves. • Planning, tracking and achieving Project KPIs & performance in line with Company’s asset working program. • Prepare and publish the Area Maintenance Look Ahead schedules and facilitate Look Ahead and Daily Planning meetings. • Ensure maintenance work is focused on planned activities and executed according to the agreed schedule. • Ensure the maintenance schedule is in accordance with corrective maintenance priority setting. • Ensure that the Area Maintenance execution backlogs are continuously monitored and maintained at agreed minimum level. • Ensure support for the area maintenance supervisors with the development of minor contract scope and counter estimates. • Ensure plant availability by maintaining an opportunity shutdown schedule including spare-parts for any outstanding corrective maintenance work. • Ensure Integrated activity scheduling & Resource levelling of Maintenance jobs along with Campaign shutdowns, Major / Minor equipment Overhauls / shutdowns & Minor Pits jobs. Show less

    • Finland
    • Industrial Machinery Manufacturing
    • 700 & Above Employee
    • Trainee Project Engineer
      • Aug 2010 - Dec 2010

      Liberty Power Tech Ltd, IPP Faisalabad • Involved in commissioning of aux. boiler and waste heat recovery boilers. • Performed overhaul of separators for fuel and lube oil. • Involved in commissioning of 11 X Wartsila 18V46 engines. • Involved in commissioning of RO plant. • Involved in clearing the punch list of waste heat recovery boilers.

Education

  • Construction Management Institute of the USA
    Diploma of Education, Forensic Scheduling
    2023 - 2033
  • University of Engineering and Technology, Taxila
    Bachelor of Engineering (BEng), Mechanical Engineering
    2006 - 2010
  • Forman Christian Colege Lahore
    FSc
    2004 - 2006

Community

You need to have a working account to view this content. Click here to join now