Erald Hasanaj
Civil Engineer at GR Albania- Claim this Profile
Click to upgrade to our gold package
for the full feature experience.
-
English -
Topline Score
Bio
Credentials
-
Profesional License
Ministry of Urban Development - AlbaniaSep, 2017- Nov, 2024
Experience
-
GR Albania
-
Albania
-
Environmental Services
-
1 - 100 Employee
-
Civil Engineer
-
Oct 2017 - Present
Job Description: Design of hydraulic structures, design of water supply systems, design of sewer systems; Participation on projects: Date May 2018 Title: “Feasibility study for the: HPP - Valamara on Grabova River” Location: Elbasan District Developer: “HIDRO VALA” Ltd & “ERGI” Ltd Date April 2018 Title: "Feasibility study for the construction of the naval shipyard, in Durresi Harbour" Location: Durres Harbour Developer: APM Ltd Date April 2018 Title: Utilization of hydropower of HEPP – Kotka on Tomorica River Location: Elbasani District Developer: AON ENERGY” Ltd & “EL-BU 2009” Ltd Date February 2018 Title: Implementation Project / Construction of the Hydropower Plant Grabova 2 on the basin of Grabova stream Location: Elbasani District Developer: H.K Hec Grabova 2” Ltd Date February 2018 Title: Implementation Project / Construction of the Hydropower Plant Grabova 1 on the basin of Grabova stream Location: Elbasani District Developer: “Grabova Hydropower” Ltd Date November 2017 Title: Implimentation Projects "Construction of the Hydropower Plant Cascade on Shushica River Location: Shushica River, Vlora District Developer: “Shushica Hydropower” Ltd Show less
-
-
-
-
Site Engineer
-
Feb 2015 - Oct 2017
Project: Rehabilitation of 11 Dams (Located in Kukes,Fier,Berat,Korce and Murriz-Thane) Project: Reconstruction of “Loro Borici” stadium located in Shkodra Project: Construction of Gjirokastra “Water Supply” Project: “Rehabilitation of 5 irrigation schemes”(Krutje,Terbuf,Strum,Kurjan and Koshnica) located in Lushnje,Divjake,Patos,Roskovec and Devoll Project: Rehabilitation of 11 Dams (Located in Kukes,Fier,Berat,Korce and Murriz-Thane) Project: Reconstruction of “Loro Borici” stadium located in Shkodra Project: Construction of Gjirokastra “Water Supply” Project: “Rehabilitation of 5 irrigation schemes”(Krutje,Terbuf,Strum,Kurjan and Koshnica) located in Lushnje,Divjake,Patos,Roskovec and Devoll
-
-
-
3a Group
-
Sarande ,Albania
-
Site Engineer
-
Jun 2014 - Jan 2015
Project: 110 kV OHL South Albania, Lot 2 Contract no: OST-110-SA-LOT-2 Title: Section West OHL 110kV D.C BABICA-SARANDE - Construstion of towers. ( Towers up to 37m high). Power trasmission lines. Project: 110 kV OHL South Albania, Lot 2 Contract no: OST-110-SA-LOT-2 Title: Section West OHL 110kV D.C BABICA-SARANDE - Construstion of towers. ( Towers up to 37m high). Power trasmission lines.
-
-
-
Kalivac
-
Sarande, Albania
-
Site Engineer
-
Feb 2012 - Jun 2014
Kalivac HPP, Tepelene - Construction of diversion gallery (horseshoe shape with h=8.5m and b=10m) - Shotcrete works (8000m2 shotcrete works) - Slope reinforcement with anchoring and shotcrete - Bridge construction on Vjosa river, (80m long), with four openings and with pilots built 20m deep on river bad. Concrete works, concrete works on presence of water, drainage Earthworks , excavation and backfilling Kalivac HPP, Tepelene - Construction of diversion gallery (horseshoe shape with h=8.5m and b=10m) - Shotcrete works (8000m2 shotcrete works) - Slope reinforcement with anchoring and shotcrete - Bridge construction on Vjosa river, (80m long), with four openings and with pilots built 20m deep on river bad. Concrete works, concrete works on presence of water, drainage Earthworks , excavation and backfilling
-
-
Education
-
Polytechnic University of Tirana, Faculty of Civil Engineering
Master of Science (MSc), Hydraulic and Hydrotechnic Department