Edwin Tsz Ho YIP
Design Manager at AUB Limited- Claim this Profile
Click to upgrade to our gold package
for the full feature experience.
-
Cantonese Native or bilingual proficiency
-
English Full professional proficiency
-
Mandarin Native or bilingual proficiency
Topline Score
Bio
Experience
-
AUB Limited
-
Hong Kong
-
Building Materials
-
1 - 100 Employee
-
Design Manager
-
May 2023 - Present
- Design development based on tender drawings and contracts - Deliver shop drawings based on detailed integration with suppliers / factory drawings, architects / designers inputs, ELV and other technical advice and requirements - Advise on the technical feasibility and risks of the projects in the pre-sales phase - Design coordination and trouble-shooting with all parties involved - Design development based on tender drawings and contracts - Deliver shop drawings based on detailed integration with suppliers / factory drawings, architects / designers inputs, ELV and other technical advice and requirements - Advise on the technical feasibility and risks of the projects in the pre-sales phase - Design coordination and trouble-shooting with all parties involved
-
-
-
Costa Coffee
-
United Kingdom
-
Retail
-
700 & Above Employee
-
Barista Maestro
-
Nov 2022 - Apr 2023
-
-
Barista
-
Oct 2021 - Nov 2022
-
-
-
Scenario
-
Hong Kong
-
Software Development
-
1 - 100 Employee
-
Scheduler
-
Aug 2018 - Nov 2020
Hong Kong Disneyland Resort Project - GC29 Castle Hub - Issued weekly and monthly progress reports by Primavera P6 and Microsoft Project - Planned and forecasted the project milestones based on site situation biweekly - Assisted Lead Scheduler to issue Extension of Time (EOT) reports Hong Kong Disneyland Resort Project - GC29 Castle Hub - Issued weekly and monthly progress reports by Primavera P6 and Microsoft Project - Planned and forecasted the project milestones based on site situation biweekly - Assisted Lead Scheduler to issue Extension of Time (EOT) reports
-
-
-
-
Project Coordinator
-
Mar 2017 - Aug 2018
HY/2014/05 Hong Kong-ZhuHai-Macao Bridge Hong Kong Boundary Crossing Facilities - Remaining Ancillary Buildings and Facilities(Contract Sum HK$2 Billion, approx. £190 Million) - Assisted Construction Manager to supervise and inspect the builder works installation and tests - Coordinated with the client, consultant and contractors to issue and submit design shop drawings, materials submission - Assisted in-house claiming consultant to issue Notice of Claims (NOCs) HY/2014/05 Hong Kong-ZhuHai-Macao Bridge Hong Kong Boundary Crossing Facilities - Remaining Ancillary Buildings and Facilities(Contract Sum HK$2 Billion, approx. £190 Million) - Assisted Construction Manager to supervise and inspect the builder works installation and tests - Coordinated with the client, consultant and contractors to issue and submit design shop drawings, materials submission - Assisted in-house claiming consultant to issue Notice of Claims (NOCs)
-
-
-
H.H. Robertson Limited
-
Mining
-
Senior Project Coordinator
-
Aug 2015 - Feb 2017
MTR Contract 1112 – Shatin to Central Link - Hung Hom Station and Stabling Sidings MTR Contract 1002 - Kwun Tong Line Extension - Whampoa Station and Overrun Tunnel MTR Contract 1001 - Kwun Tong Line Extension - Yau Ma Tei to Whampoa Tunnels and Ho Man Tin Station - Coordination and liaison with client, main contractor and other sub-contractors regarding shop drawings design and site installations - Supervised the site installation progress to assist the main contractor to meet the milestones - Assessed the project progress to assist the Quantity Surveyor for the payment application Show less
-
-
-
-
Technical Officer
-
Apr 2013 - May 2015
ASD Project – Fire and Ambulance Services Academy at Tseung Kwan O Residential Development at Lai Ping Road, Kau To Shan - Prepared BD General Building Plans (GBP) submission and calculation - Assisted architects to prepare layout plans, elevations, sections and details drawings by AutoCAD ASD Project – Fire and Ambulance Services Academy at Tseung Kwan O Residential Development at Lai Ping Road, Kau To Shan - Prepared BD General Building Plans (GBP) submission and calculation - Assisted architects to prepare layout plans, elevations, sections and details drawings by AutoCAD
-
-
Education
-
Hong Kong Institute of Vocational Education
Higher Diploma, Architectural Design and Technology