Experience

    • Iran
    • Construction
    • 1 - 100 Employee
    • Executive Vice President
      • May 2021 - Present

      The main road to Shahriar Dam

    • Site Manager
      • Apr 2020 - May 2021

      Tehran-North Freeway

    • Senior surveyor
      • Apr 2013 - Apr 2020

      Uma Oya Multi-purpose Development Project site southeast of Sri Lanka is located 200 km east of Colombo Uva Province.The project includes Puhulpola RCC Dam over Uma Oya River and Dyraaba RCC Dam across Mahatotilla Oya River.A link tunnel from Puhulpola Reservoir to Dyraaba Reservoir,a headrace tunnel (powerhouse) from Dyraaba Reservoir towards the powerhouse,a concrete lined vertical shaft,a surge tank at the upstream of vertical shaft convey water to the under ground powerhouse.The outflow from the powerhouse is discharged to Alikota Area through tailrace tunnel.Annual energy generation of 290 GWh via 2x60 MW power plant units.http://www.parlsrilanka.org/issues/multi-purpose-project/item/181-uma-oya-multi-purpose-developmental-project Show less

    • Surveyor
      • Nov 2009 - Mar 2013

      Hajilar dam Hajilar dam

    • Surveyor
      • Mar 2008 - Oct 2009

      Siyah bisheh dam

    • Surveyor
      • Jul 2003 - Feb 2008

      The Ostour (Sharyar) Dam project is located on Ghezel-Ozan River, about 38 kilometres downstream of Mianeh in the north-west region of Iran. A 135 metre high concrete arch dam will be constructed to store water for the irrigation of the intermediate agricultural lands, between Ostour and Sefid-Rud storages, and to satisfy the demands downstream of the Sefid-Rud Dam. The deposited sediment reduced the capacity of the storage to about 50 per cent of the initial 1,700 m3. The storage level was fixed at elevation 1,035 masl. The stored water is proposed to be used for irrigation and forced removal of sediment in the Sefid-Rud storage reservoir downstream. Show less

Education

  • University of seraj Tabriz
    Master's degree, Civil - Geotechnics