Arun Valleti
Construction Manager - Electrical Substation at Engineering Solutions Electromechanical & General Contracting LLC- Claim this Profile
Click to upgrade to our gold package
for the full feature experience.
-
English Professional working proficiency
-
Hindi Professional working proficiency
-
Telugu Full professional proficiency
-
Tamil Full professional proficiency
-
Malayalam Limited working proficiency
-
Arabic Elementary proficiency
Topline Score
Bio
Credentials
-
QMS TRAINING
L&T Infrastructure Finance Co Ltd
Experience
-
Engineering Solutions Electro Mechanical & General Contracting LLC
-
United Arab Emirates
-
Construction
-
1 - 100 Employee
-
Construction Manager - Electrical Substation
-
Jul 2019 - Present
-
-
-
Jazeera Emirates Power ( JEP)
-
Dubai, United Arab Emirates
-
SITE MANAGER - Electrical
-
Sep 2016 - Present
Site Manager for 132 /11 kV Substations Site Manager for 132 /11 kV Substations
-
-
-
National Contracting Company Ltd
-
FUJAIRAH, UAE
-
SITE MANAGER
-
Jul 2013 - Sep 2016
Project: E19/2012(1): 33/11 kV Substation works in North & Eastern areas of Northern Emirates. Client: Federal Electricity & Water Authority (FEWA) Consultant: Energo Project Entel (EPE) Tasks performed Overall Site In charge for 3nos. New & 2 nos. Ext. 33/11 kV SS from Civil works to Commissioning works Site co-ordination with the Project Manager &Design team for approval & issue of IFC drawings to Site. Leading the site team of different types of skilled persons and achieve the productive work at site. Micro Level Scheduling & Supervising site activities and supporting Sub Contractors & Vendor team at Site. Site Execution in line with Scope, Contractual procedure & tech. specs/standards as per client requirements. Resource (Material & Manpower) planning allocation & controlling depends on the project phase. Co-ordination for Site progress meetings with the client, consultant, Subcontractor & vendors at site. Review of all vendor drawings such as HVDT, GIS, AIS, NER, C&R Panel, Cap Bank, Aux. Tr. &Cables etc. Technical submittals, Material estimation, approval & monitoring to arrange timely as per site requirement. Show less
-
-
-
National contracting company (NCC)
-
Muscat -Oman
-
Sr. Project Engineer-Electrical
-
Jan 2011 - Jul 2013
Project: 74/2010: Construction of New 220/132 kV GIS Grid Station with 400 kV OHL & 220 KV Cabling works. Client: Oman Electricity Transmission Company (OETC) Consultant: Energo Project Entel (EPE) Tasks performed Co-ordination with the Project Manager and Design team for approval & issue of IFC drawings to Site. Review of GIS switchgear Layouts & related equipment drawings as per requirement of execution stage. Co-ordination for arrangement of meetings with the client, consultant and vendors at site. Review of all vendor drawings such as Power Tr., GIS, NER, EAT, C&R Panel, Aux. Tr., Power Cables etc. Site Erection, installation and Co-ordination works in new 220/132/33/11 kV substation. 220 kV GIS, 132 kV GIS & 500 MVA Transformer erection & installation works at the site level. Technical submittals, Material planning, monitoring, receipts, inspection and installation as per specifications. Preparation of control cable and power cable schedule and implementing at site level. Shut down works for the extension of 132/33/11kV Switch yard works in existing site. Show less
-
-
-
GECO M&E LTD
-
United Arab Emirates
-
Construction
-
500 - 600 Employee
-
PROJECT ENGINEER
-
Apr 2010 - Dec 2010
Project: Construction of 132/33 KV Substation works and Modification Works Project: Construction of 132/33 KV Substation works and Modification Works
-
-
-
Larsen & Toubro
-
India
-
Construction
-
700 & Above Employee
-
Sr. ELECTRICAL ENGINEER
-
Sep 2007 - Mar 2010
Project: Expansion & Reinforcement of 132/ 33/11 kV Substations & Network in Al Ain, ABU DHABI. Consultant: PB Power Client: ADWEA/ AADC/ADDC Tasks performed Planning, monitoring and execution of Project time Schedules as per Work Base System. Technical submittals, Material planning, approvals, receipts, inspection and installation as per specifications. Preparation of Method Statements & work Procedures for site erection & commissioning activities. GIS switch gear erection; installation and Co-ordination with solid experience. Control/Protection panels & SCADA/Telecom panel's erection, installation and commissioning works. 25 MVA Power Transformer Erection Capacitor Banks Installation and LVAC/DC Panels installation Power, Control, FO and Telecom Cable Schedule Preparation, routing with Cable ladders/Trays & Supports. UG Power Cables & FO cable works- Route approvals, laying, testing, termination and energizing works. Co-ordination with design team, providing field data for modification of remote end works in ex-stations. Show less
-
-
-
ICOMM Tele Limited
-
India
-
Telecommunications
-
400 - 500 Employee
-
PROJECT ENGINEER
-
Jan 2006 - Sep 2007
Project: Conversion of 3-* LT to HT network in HVDS Project; Client: AP DISCOM / AP TRANSCO Tasks performed Design, drafting and approval of 11KV & LT 3-* Network Diagrams using Auto CADD. Site survey, peg markings route approvals with local authorities as per approved drawings. Conversion of LT 3-* Network into HT Network in High Voltage Distribution System(HVDS) Supervision of Erection, Testing and Commissioning of Pole mounted Transformers including AB cable. Cable Schedule Preparation and Co-ordination for BOQ Inspections at site. Show less
-
-
-
Klen & Marshals
-
Tirupati Area, India
-
MAINTENANCE ENGINEER
-
Apr 2000 - Apr 2005
Maintenance of 11 kV 2MVAR capacitor Banks and associated works in Tirupati Region. Maintenance of 11 kV 2MVAR capacitor Banks and associated works in Tirupati Region.
-
-
-
-
SERVICE ENGINEER
-
Apr 1999 - Apr 2000
Project: System Expansion& Improvement for 11 kV Network, Southern Region, AP, INDIA. Client: APSPDCL (DISCOM) Task performed Erection, installation of 132 kV, 33 KV &11 kV switch yards in primary Stations & Grid stations. Erection, installation, commissioning and Maintenance of 11 KV, 5 MVAR detuned capacitor/reactor banks. Data down loading from MVAR meter and Tri-vector meter for Energy evaluation purpose. Project: System Expansion& Improvement for 11 kV Network, Southern Region, AP, INDIA. Client: APSPDCL (DISCOM) Task performed Erection, installation of 132 kV, 33 KV &11 kV switch yards in primary Stations & Grid stations. Erection, installation, commissioning and Maintenance of 11 KV, 5 MVAR detuned capacitor/reactor banks. Data down loading from MVAR meter and Tri-vector meter for Energy evaluation purpose.
-
-
Education
-
Sri Venkateswara University
Bachelor's Degree, Electrical and Electronics Engineering -
Sri Venkateswara University
Diploma in Electrical & Electronic Engineering (DEEE), Electrical and Electronics Engineering