Ahmed Hassan , PMP®,PMI-RMP®,Approved Aramco and Bechtel
Project Manager at Arabian Gulf Construction Co. Ltd. ( AGC )- Claim this Profile
Click to upgrade to our gold package
for the full feature experience.
-
English Professional working proficiency
-
Arabic -
Topline Score
Bio
Credentials
-
Healthy and Safety Bechtel Certification
Royal Commission for Jubail and YanbuMay, 2013- Nov, 2024 -
Royal Commission approval as a Construction Manager
Royal Commission for Jubail and YanbuMay, 2012- Nov, 2024 -
PMI Risk Management Professional (PMI-RMP)®
Project Management InstituteFeb, 2021- Nov, 2024 -
Project Management Professional (PMP)
Project Management InstituteNov, 2020- Nov, 2024 -
Project Management Professional (PMP)®
Project Management InstituteNov, 2020- Nov, 2024
Experience
-
Arabian Gulf Construction Co. Ltd. ( AGC )
-
Saudi Arabia
-
Construction
-
1 - 100 Employee
-
Project Manager
-
Mar 2021 - Present
1.Project: Construction of Well Core Facility Project, Aramco Dhahran, KSA Project Value: 165 Million Project Description: The scope of work of this BI is to provide integrated Well Core Facility in Dhahran to consolidate the storage, handling and characterization operations of the Well Cores and cutting. The new integrated Well Core Facility will be with a total area of about 14,670 Square Meters (SM), which consists of 7,000 SM of core storage space, 1,183 SM of core handling space, 1,722 SM of office space, 2,485 SM Laboratory spaces, 1,750 SM of building support space and 530 SM for the mechanical rooms. A car park that can accommodate a minimum of 175 shade parking spaces shall also be provided. Project scope also include all types of excavation including rocks regardless of depth including, but not limited to removal and disposal of excess material to a dump site approved by Aramco Show less
-
-
-
AL-AYUNI Investment and Contracting Company
-
Construction
-
700 & Above Employee
-
Project Manager
-
Apr 2020 - Mar 2021
-
-
Construction Manager
-
Jul 2017 - Apr 2020
1)Project: Dareen East Beach Phase 2 and Park Improvement. Project value: SAR. 183 Million Project Description: The project involves the Construction of 6 km Strom drainage, 1. 3 km Sanitary Waste Water collection system, 5 Lift Stations, 14 km Potable and Fire Water Network, 65 km Irrigation & Distribution System, Landscape, 80000 sqm Asphalt Road, 180000 sqm lanscaping areas ,5000 palm trees,10 no pergolas , one amptheater , 10 units life guardstaions , two fountains, 7 public toilets, 70000 sqm coloured Interlocking Paver tiles,25000 sqs concrete paving 3 no Unit Substations, Street Lighting networks, LV cable, Medium voltage cable works, Telecommunication and Instrumentation works. Show less
-
-
-
Kier Group
-
United Kingdom
-
Construction
-
700 & Above Employee
-
Construction Manager
-
Jun 2013 - Jun 2017
*Project: Mutrafiah Sabic Housing Project Phase-IV (PKG-1), Sabic& Royal Commission. Key Responsibilities:-Responsible for the execution of all assigned projects meeting the company's contractual obligations and the client's needs and expectations.Monitor overall productivity and efficiency of all supervised staff on projects and provide training and development opportunities. Ensure the completion of assigned jobs within the contractual requirements of the client, and within the allocated time, budgeted cost, and quality standards with a perfect safety record.Arrange for timely preparation and approval of all documents as required by the project scope of work or as requested by the Project Manager, Assist Project Manager in timely issuance of invoices for assigned projects, and in timely certification and collection of invoiced amounts, and in preparation of variation orders, and in completing the monthly subcontractor payment certificates on time. Arrange for Ordering materials/equipments and Technical evaluation of the bids for the procurement of materials/equipments for discipline. Conduct meetings with all supervised staff to effectively communicate and clarify project requirements.Participate in meetings with the Project Manager, Client and third Parties, Job scopeReview and study all the IFC drawings which related to our scope.Prepare and submit the execution plan to the client representative.Prepare and submit the construction plan to the client representative.Prepare and submit all the construction method statements to the client representative.Assist the planning department to prepare the schedule plan for the project.Assist the quality control department to prepare the quality plan and ITPS for the project. Execute all the underground utilities including (rough grading, storm drainage network, sewerage drainage network, potable water network, irrigation network, lift station, pump station, duct banks and sidewalks). Show less
-
-
Construction Manager
-
Jul 2013 - Dec 2014
*Client: Saudi Aramco*Project Management: Saudi Aramco*Consultant: Saudi Aramco.*Budget: 30 billions S.R.*Job description:-Act competently with due diligence to fully maintain the interests of the company in all business activities. Monitor overall productivity and efficiency of all supervised staff on projects. Ensure the completion of assigned jobs within the contractual requirements of the client, and within the allocated time, budgeted cost, and quality standards with a perfect safety record. Introduce new methods of construction, equipment, and machinery to improve the construction process. Arrange for timely preparation and approval of all documents as required by the project scope of work or as requested by the Project Manager, consisting of: Drawings, specifications, construction scopes of work, Data sheets, Material take Off. Assist Project Manager in timely issuance of invoices for assigned projects, and in timely certification and collection of invoiced amounts, and in completing the monthly subcontractor payment certificates on time. Participate in meetings with the Project Manager, Client and third Parties, involving supervised staff as required, to communicate and clarify interfaces, requests, decisions, approvals, proposals, status, responses.Job Responsibilities: Review and study all the shop drawings which related to Scope at project. Execute 265,000 square meters concrete paving at Train 400,300,200 and 100 ,KOD Area and Flare Area at Package 1. Execute 4100 thickening footings as a pipe supports under the pipe racks at Train 400,300,200 and 100, KOD Area and Flare Area. Execute 166,000 squared meters asphalt paving at Package and Package 3.Execute 16 storm drainage structures scattered at Package 1.Execute 12 underground sumps starting from excavations up To finishing the external and internal coatings . Show less
-
-
-
Al Fozan Holding
-
Saudi Arabia
-
Investment Management
-
1 - 100 Employee
-
Construction Manager
-
Mar 2012 - Jun 2013
Project: Construction of City Plant Nursery Medical Warehouse. *Client: Royal Commission. *Project Management: *Consultant: Bechtel Engineering Company. *Job description:- Act competently with due diligence to fully maintain the interests of the company in all business activities. Responsible for the execution of all assigned projects meeting the company's contractual obligations and the client's needs and expectations. Monitor overall productivity and efficiency of all supervised staff on projects and provide training and development opportunities. Ensure the completion of assigned jobs within the contractual requirements of the client, and within the allocated time, budgeted cost, and quality standards with a perfect safety record. Introduce new methods of construction, equipment, and machinery to improve the construction process. Arrange for timely preparation and approval of all documents as required by the project scope of work or as requested by the Project Manager, consisting of: Drawings, specifications, construction scopes of work, calculations, Data sheets, Material take Off, BOQ. Prepare methods of statements as needed for the project. Assist Project Manager in timely issuance of invoices for assigned projects, and in timely certification and collection of invoiced amounts, and in preparation of variation orders, and in completing the monthly subcontractor payment certificates on time. Arrange for Ordering materials/equipments and Technical evaluation of the bids for the procurement of materials/equipments for discipline. Conduct meetings with all supervised staff to effectively communicate and clarify project requirements. Participate in meetings with the Project Manager, Client and third Parties, involving supervised staff as required, to communicate and clarify interfaces, requests, decisions, approvals, proposals, status, responses. Show less
-
-
-
IPMC
-
Saudi Arabia
-
Business Consulting and Services
-
1 - 100 Employee
-
Senior Civil / Infrastructure Engineer
-
Mar 2009 - Feb 2012
Senior Civil / Infrastructure Engineer IPMC - International Project Management Co. *Project:AL Khobar Lakes Development (Villages 1&2) *Client: Emaar Middle East. *Project Overview: Construction of gated communities – two villages contains 474 villas on two stages: 1- Construction of 474 villas 2- Infrastructure works for 1 Villages with total Area 400,000.000 m2 *Project Management: CIMS *Project Designer: ARABIAN ARCHTECTURE - PARSONS *Consultant: - International Projects Management Co. - Saudi Consult *Budget:1300 Million SR *Job Responsibilities: •Design Implementation for Structural package-drawings •Design Implementation for infra-structure package-drawings •Prepare /study/ Review structural/infrastructure shop drawings •Prepare/study / Monitoring time schedules & progress evaluation of the project. •Undertake all Inspection duties & survey works for all construction activities on the site for 474 villas, walkways & landscape as a team leader •Undertake Inspection duties & survey works for all infrastructure activities (Rough grading, sewerage network, potable water network, irrigation network, storm water network, electrical network, roads, landscape, hard cape, Lakes,RO plants, lift stations, sewerage treatment plant, irrigation tanks.... etc) as a team leader •Monitor the operations and working of staff on the site •Ensure that the said rules, regulations and guidelines are followed without any exception •Review, study & Preparation of technical notes, structural rectifications, method statements, site instructions and site modifications for all activities. •Study / Review & comment on the monthly payments (interim payments) submitted by contractors. •Monitor and Control the contractor`s progress and quality by weekly/monthly reports and managerial meetings. •Chair and conduct Progress meetings, Quality and Safety meetings •Test and Commission related works after completion of construction and ensure its compliance with specifications and standards. Show less
-
-
Education
-
Alexandria University