    • Utilities
    • 1 - 100 Employee
    • Shift Manager Operations
      • May 2015 - Present

      • Actively participated/supervised the commissioning and testing of 2x31.2MW HTC Steam Turbine & 2x155 TPH 110 bar & 535°C high pressure/temperature travelling grate boilers, Manufactured by Wuxi China & BOP of 2x31.2MW Chiniot Power IPP Project including 132kV switchyard, 11kV & 400V electrical system, EDGs, bagasse fuel handling & Electrostatic Precipitator (ESP) systems. • Major responsibilities include Complex Startup, Operation, Shutdown, emergency handling, troubleshooting, safety permits issuance, coordination with maintenance departments, preparing daily generation sheets and performance monitoring. • To communicate with Power purchaser during complex startup, shutdown or trip and take effective action according to Energy Purchase Agreement. Show less

    • Oil and Gas
    • 1 - 100 Employee
      • Aug 2012 - May 2015

      • Operations of 41MW CHPP Unit including 200 TPH boiler & 41 MW SST 300 SIEMENS Turbine, Electrical Control Room, 65 TPH boiler, demineralization plant, Air Compressors within prescribed parameters.• Hands on experience on DCS control system for main plant control room operation.• Knowledge on power plant basics, water chemistry, electrical system of power plant including equipment protection and basic control system.• Responsible for power plant operation and trouble shooting, equipment start-up and shutdown.• Equipment performance/condition monitoring, reporting defects to the maintenance teams, keeping chemical parameters within permissible limits, carrying out electrical switching. • Preparing daily generation statistics for HFO & Natural Gas fuel. Show less

      • Nov 2010 - Jul 2012

      • Worked on 3x120MW GE PG9171E Gas Turbines, 3 HRSG’s, 1x190MW HTC Steam Turbine & BOP of BQPS-II 560MW CCGT Project in Bin Qasim, Karachi.• Installation and Commissioning activities of 560 MW CCPP Project.• Performing surveillance of all static, rotating and packaged equipment installation work in progress on a continuing basis includes storage tanks, vessels, columns, heat exchangers, compressors, pumps, packaged equipment.• Preliminary design and engineering of pipelines according to codes and standards.• Erection/Installation and Site Inspections.• Progress monitoring, Planning/Scheduling & Documents controlling. Show less

Education

  • U. C. E. & T. Bahauddin Zakariya University
    Bachelor's degree, Mechanical Engineering