Feb 2022 - Present
Roles & Responsibilities: • Responsible for the consultancy job for the construction of 360 MW Combined Cycle Power Plant at Mymensingh Bangladesh. • Coordinating with EPC Contractor and troubleshooting the issues related to drawings & execution. • Coordinating with site professional & ensure project is running smoother & as per the milestone schedule. • Weekly project progress / review meeting with subcontractors & internal civil professional. • Reporting to CEO (Owner Side) RPCL Bangladesh.
-
-
-
M/s Hans Construction
-
Bhubaneshwar, Odisha, India
-
Head of Civil Engineering
-
May 2018 - Jan 2022
Roles & Responsibilities: • Liaison with Government of Odisha for allocation of Land & Funds for Ongoing Projects. • Review of Drawings & strategy implementation for the executions. • Coordinating with Subcontractors & Project Team on daily basis. • Hiring Professionals as per project requirement. • Participation / Monitoring Tender team for new / upcoming projects in Bidding Stage. • Implementing HSE & QA/QC Standard as per client requirement. • Ensure that all the materials (Civil, Electrical & Mechanical) required for project execution arrived on time to avoid interruption in work progress. • Conducting weekly review meeting with project team (Civil, Mechanical, Electrical, HSE, Accounts, Procurement & Hr & Admin). • Constant monitoring on all ongoing projects, Timely preparation & submission of Bills & follow for payment till the project completion. • Preparation of Checklist & Handing over completed projects to the client. • Reporting to Managing Director.
-
-
-
-
Project Director
-
Jul 2015 - Mar 2018
Roles & Responsibilities: • In charge of Execution & Procurement activities for construction of 1710 MW Combined Cycle Power Plant – EPC Project along with administrative building (G+4) Built up are 85000 SQ. FT. • Inspecting the work progress as per planned schedule to achieve the milestone schedule, Managing Subcontractors, resolving Civil & MEP related issues & ensuring safety as per Bechtel laws & policies. • Ensuring that the Construction & Procurement process are moving in accordance and conformity with the approved procedure and in compliance with the company QA/QC & HSE Policy. • Coordinating with accounts team to release the subcontractor payment in timely manner & maintain healthy relationship for the growth of the organization. • Reported to CEO. (Mr. Abdullah).
-
-
-
HADI HAIDER
-
1 - 100 Employee
-
Sr. Project Manager
-
Dec 2013 - May 2015
Roles & Responsibilities: • Responsible for the execution of 325 million SAR 115 KVA substation and underground transmission line project under Royal commission Jubail. • Overview the work progress as per planned schedule to achieve the milestone, Managing Subcontractors & inspecting the RFIs Raised by the Subcontractors. • Ensuring site safety as per Bechtel standard & Client requirement. • Reported to Project Director & MD (Mr. Mohammad & Mr. Zafar Hussain). Roles & Responsibilities: • Responsible for the execution of 325 million SAR 115 KVA substation and underground transmission line project under Royal commission Jubail. • Overview the work progress as per planned schedule to achieve the milestone, Managing Subcontractors & inspecting the RFIs Raised by the Subcontractors. • Ensuring site safety as per Bechtel standard & Client requirement. • Reported to Project Director & MD (Mr. Mohammad & Mr. Zafar Hussain).
-
-
-
IVRCL Infrastructures and Projects Ltd
-
India
-
Construction
-
700 & Above Employee
-
Senior General Manager
-
May 2012 - Nov 2013
Roles & Responsibilities: • In charge for execution of 800 x 3 MW Super Thermal Power Plant of NTPC at Kudgi Karnataka India. Budget 475 Cr along with construction of time office & Bachelor’s Accommodation (G+7) Built-up area – 82000 SQ. FT. • Also responsible for Civil Part of Metro Project in Bangalore. • Reported to Regional Head – Bangalore. (Mr. K Satish Kumar). Roles & Responsibilities: • In charge for execution of 800 x 3 MW Super Thermal Power Plant of NTPC at Kudgi Karnataka India. Budget 475 Cr along with construction of time office & Bachelor’s Accommodation (G+7) Built-up area – 82000 SQ. FT. • Also responsible for Civil Part of Metro Project in Bangalore. • Reported to Regional Head – Bangalore. (Mr. K Satish Kumar).
-
-
-
Gayatri
-
India
-
Construction
-
500 - 600 Employee
-
General Manager Civil
-
Feb 2009 - Mar 2012
Roles & Responsibilities: • In charge of 978 Cr RMHS (Raw material handling system) project of TATA steel Ltd at Kalinganagar, Orissa. • Responsible for railways siding work along with construction of administration building. • Reported to Executive Director (Mr. Sitaram). Roles & Responsibilities: • In charge of 978 Cr RMHS (Raw material handling system) project of TATA steel Ltd at Kalinganagar, Orissa. • Responsible for railways siding work along with construction of administration building. • Reported to Executive Director (Mr. Sitaram).
-
-
-
Jindal Steel & Power Ltd.
-
India
-
Mining
-
700 & Above Employee
-
Deputy General Manager
-
Apr 2007 - Jan 2009
Roles & Responsibilities: • In charge for construction of township, school building, administrative building & 12 MTA vertical DRI Project and Railway siding work. • Township Construction area included quarters for senior staff. {2 & 3 BHK – G+6 Residential Complex} Total Built-up area – 157000 SQ. FT. • Reported to Executive Director (Mr. Rajesh Jha) (Current CEO of Adani Group). Roles & Responsibilities: • In charge for construction of township, school building, administrative building & 12 MTA vertical DRI Project and Railway siding work. • Township Construction area included quarters for senior staff. {2 & 3 BHK – G+6 Residential Complex} Total Built-up area – 157000 SQ. FT. • Reported to Executive Director (Mr. Rajesh Jha) (Current CEO of Adani Group).
-
-
-
Government of Odisha
-
Government Administration
-
500 - 600 Employee
-
Sr. Technical Consultant
-
Jan 1990 - Mar 2007
Roles & Responsibilities: • District head for Project Management and Execution of School Buildings. More than 6250 school buildings have been constructed under my leadership. • Reported to District Chief / Collector and State Project Director. Roles & Responsibilities: • District head for Project Management and Execution of School Buildings. More than 6250 school buildings have been constructed under my leadership. • Reported to District Chief / Collector and State Project Director.
-
-
Education
-
SJM Institute of Technology (SJMIT)
Bachelor of Engineering, Civil Engineering -
Sambalpur University
Intermediate, PCM